Grand Canyon MGT455 week 2 quiz 2

Question # 00096349 Posted By: kimwood Updated on: 08/24/2015 08:36 AM Due on: 09/23/2015
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

· A certain project activity has an ES (early start) of 10 and a late start (LS) of 14. The total slack for this activity is:

14


9


4


5

· A certain project activity has an EF (early finish) of 11 and a late finish (LF) of 11. The total slack for this activity is:

-8


-12


0


24

· Activity C has two predecessor activities: Activity A and Activity B. The EF (early finish) of Activity A is 5. The EF (early finish) of Activity B is 7. Therefore, the ES (early start) of Activity C is:

5


6


7


8

· A given project’s expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates. What is the probability that the project will finish on or before 50 days.

0.50


1.00


0.00


0.25

· A given project’s duration along its critical path is 33 days and the total slack for one of the activities is 1 day. The planned finish time for the project is:

31 days


33 days


32 days


34 days

· A given project’s expected duration along its critical path is 32 days. The project’s standard deviation along its critical path is 4 days. What is the probability that the project will finish on or before 35 days.

0.78230


0.27337


0.77935


0.77337

· For the project schedule below, if activity D gets delayed by 1 day, the project end date will get delayed by:

·

Enlarged View

0 days


1 day


2 days


3 days

· For the project schedule below, if activity C gets delayed by 1 day, the project end date will get delayed by:

·

Enlarged View

0 days


1 day


2 days


3 days

· A certain project activity has an EF (early finish) of 11 and a late finish (LF) of 16. The total slack for this activity is:

6


16


-10


5

· A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. The duration of the project is ________.

30 days


5 days


40 days


35 days

· A given project’s expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The project’s standard deviation along its critical path is 2.03. The approximate computed z value is:

2.71


0.76


4.66


1.00

· Activity F has one predecessor activity: Activity E. The EF (early finish) of Activity E is 18. Therefore, the ES (early start) of Activity F is:

6


24


18


12

· For the project schedule below, the critical path is:

·

Enlarged View

A – C – E


cannot determine


A – B – C – D – E – F


B – D – F

· A certain project activity has an EF (early finish) of 29 and a late finish (LF) of 29. The total slack for this activity is:

0


23


-15


-23

· Activity C has two predecessor activities: Activity A and Activity B. Activity A has finished; however, Activity B has not yet finished. Which statement below is most accurate?

Activity C cannot start, since Activity B has not yet finished.


Activity C can start, since Activity B will eventually finish.


Activity C can start, since Activity A has finished.

Dot Image
Tutorials for this Question
  1. Tutorial # 00090688 Posted By: kimwood Posted on: 08/24/2015 08:36 AM
    Puchased By: 9
    Tutorial Preview
    the project end date will get delayed by: · Enlarged View 0 ...
    Attachments
    MGT455-quiz-2.docx (77.2 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    an...05 Rating Provide assignments on time 03/05/2018
    ela...el01 Rating Give brilliant academic assistance 06/25/2017
    n0...11 Rating The presentation of work is very effective 01/10/2017
    as...00 Rating Elaborated tutorials; all points covered 08/17/2016
    kur...ford Rating Fair-deal tutorials 02/29/2016

Great! We have found the solution of this question!

Whatsapp Lisa