1. Question :

Schedule forecasts are an output from which process?

Control Schedule

Monitor and Control Project Work

Develop Schedule

Close Project or Phase


Question 2. Question : Changes to the schedule baseline can be approved through:

audits.

the Perform Integrated Change Control process.

the Control Schedule process.

the critical path method.


Question 3. Question : Work performance data output from the Control Schedule process include the following except:

the deliverables that were over budget.

the deliverables that have finished.

the deliverables that have started.

the deliverables that are in progress.


Question 4. Question : Earned value management measurement(s) used to control schedule is/are:

A and C

SV

CPI

ETC


Question 5. Question : Schedule performance reviews include all of the following except:

earned value management.

fast tracking.

trend analysis.

critical path method.


Question 6. Question : Maintaining changes to the schedule baseline is performed by the __________ process.

Monitor and Control Project Work

Control Schedule

Validate Scope

Perform Integrated Change Control


Question 7. Question : Crashing for schedule compression works for:

any activity.

only activities on the critical path.

activities ahead of schedule.

activities behind schedule.


Question 8. Question : Control Schedule is in the __________ Process Group.

Executing

Planning

Closing

Monitoring and Controlling


Question 9. Question : The difference between float and buffer is:

there are two types of float and one type of buffer.

buffer is the sum of all the float in the project.

float is calculated for each activity not on the critical path, whereas buffer is calculated for chains.

the concepts are the same and define the slack time in the project.


Question 10. Question : What specifies how formal acceptance of completed deliverables will be obtained?

Requirements traceability matrix

Control Schedule process

Stakeholder management plan

Scope management plan

Dot Image
Tutorials for this Question
  1. Tutorial # 00362554 Posted By: rey_writer Posted on: 08/21/2016 05:08 AM
    Puchased By: 3
    Tutorial Preview
    The solution of saint leo prm520 quiz 3 latest 2016 july...
    Attachments
    quiz_3_.docx (58.65 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    oa...m85 Rating Instant response from the tutors 10/02/2016

Great! We have found the solution of this question!

Whatsapp Lisa