We have begun to experience a growing backlog of customer orders in the Plasti-Brack product line.For the last two to three months apparently we have had a slow creep-up of order backlog in the MLD250 department, specifically the Plasti-Brack molding group. It seems that we now have a 5 to 6 week backlog which is entirely unacceptable to our customers. As you know, our customers have been accustomed to getting orders shipped almost immediately or within a week of placing their orders. So now they don’t like to have to wait. Jack Walker and I think that this could possibly adversely affect our business since these items are so popular.It is my opinion that we need more capacity in Machine Group 251. As you know, we have four 250-Ton plastic injection molding machines, which run these six parts. However, lately one of the machines seems to be experiencing excessive downtime. There also seems to be some tool wear causing low productivity. I suggest you talk to Don Stump to get more details on the order backlog and his scheduling system. Talk to Tom Gunner in Engineering or one of his Manufacturing Engineers about the machines and tools. And you should also check with Bill Morton and someone in the Plastic Injection Molding area about the tools. And while you are talking with Bill, ask him about his opinion of capacity. Ask Don Stump his opinion as well.What I expect you to do consists of three main activities: 1) check out our capacity problem. See what we need to do to increase capacity. There is a capital budget available for the MLD2500 group - see Harvey Lund for more details. 2) We have to get our delivery time down to acceptable levels - see Don Stump for the details. 3) And while you are at, see what you can do to improve productivity and lower our costs.  I expect your report in about two weeks with your recommendations and justification.NEW INFORMATION GATHEREDThere is a high reject rate of plastic inserts coming from MG 251, as found in the Plastic-Brack Assy, MG403 – it seems to be somewhere between 12% to 20% reject rate, depending on which plastic insert.You also discover that the molding dies are very old and some of the mold cavities are closed off because of previous poor quality, which further reduces the yield rates from the standard expectations. Dies for P90, P120B, and P135 each have one cavity closed off. Swenson thinks that more should be closed off, based on his expertise and the age of these dies.New plastic injection molding dies cost $25,000 each, or $30,000 each if they are designed for quick changeover. The lead time for manufacturing these dies by an outside tool and die company is 6 weeks each.One of the four molding machines, M101, has a record of high unscheduled repair and downtime. It seems to need some minor adjustments several times per week, which is causing low uptime for it. Swenson, the molding supervisor, would like to see the machine have a complete overhaul. Dick Wrangle would like to purchase a new 250-ton molding machine. The cost to overhaul is estimated to $100,000, and the cost of a new machine is $250,000.Mark Monnin, the Purchasing Manager, tells you that there is better grade plastic resin that could be used, but it is more expensive. The better materials are RP515 at $0.28 per pound or RP625 at $0.30 per pound; the current material in use is RP502 at $0.26 per pound; the quality ranking order is RP625 > RP515 > RP502.  Monnin believes the best material, RP625, would reduce some of the scrapped parts generated by MG251. He is not sure how RP515 would do.Bill Morton, the Plant Manager, informs you that a second shift has not been approved at this time, but could be as a last resort. There is a 15% shift premium paid to those who work on the 2nd shift. Overtime could also be used, possibly 2 extra hours per day and up to 10 hours on Saturdays. OT earns employees an additional half-time for hours over 40 per week.The setup times (die changeover) in both blanking and molding are in the three and half to four and a half hour range. You asked Tom Tucker what it would take to modify these dies with quick clamps and other mechanisms so that you could reduce the setup times. Tucker said that to modify existing dies would cost about $10,000 each. Your research in this area confirms this number is in the ballpark and that setup times can be reduced to about 0.5 to 1.0 hours.Harvey Lund indicates that there is a capital budget for MLD250, of which $325,000 is available for MLD251. You can purchase machines, tools, overhauls and tool upgrades with this budget. He also says that you don’t need to spend all of it.Mike Finch, the Marketing Analyst, says that the demand rate of customer orders has not increased substantially in the last quarter, nor does he think that it is going to rise much soon. He still stands by his long term forecast over the next five years.AssignmentAnalyze the situation in the Plasti-brack product line. Diagnose the problem and possible solutions to the capacity and order backlog. Determine an appropriate plan for correcting the problem. Justify your plan and make recommendations using your knowledge of productivity, process improvement, inventory, capacity, forecasting, and quality. Write a report to the VP of Operations.ExpectationsExplore the possibilities of spending some of the capital budget on a machines and or tools. Also consider improving setup time, improving quality, increasing capacity, and determining EOQs.Determine a plan for solving this problem in the Plasti-brack product line. Consider there may be both a short-term solution and a long-term solution.Justify your plan based on the concepts of capacity management.The following is the Income Statement from the year just completed. Gross Income COGS Gross Margin PRODUCT LINE(000s) (000s) (000s)    Fasteners $        1,0107.3% $     6464.7% $         3642.6%  Cabinet Hardware $        3,24323.5% $  1,78312.9% $      1,46010.6%  Construction Hardware $        4,16530.2% $  1,87413.6% $      2,29116.6%  Decorative Hardware $        5,38839.0% $  2,58618.7% $      2,80220.3%TOTALS $      13,806100.0% $  6,88949.9% $      6,91750.1%OPERATING EXPENSES      Marketing and Advertising   $     8506.2%  Commissions, Wages & Salaries   $  1,75012.7%  Benefits   $     7705.6%  Office Expenses   $     1751.3%  Depreciation   $     7345.3%  Insurance   $     9436.8%  Fixed Energy & Utility Expenses   $     2681.9%  Miscellaneous   $     1321.0%  TOTAL OPERATING EXPENSES     $         5,62240.7%Net Income Before Taxes     $         1,2959.4%The following is the Statement of Inventories (from the Balance Sheet) for the year just ending: BeginningEndingInventories(000s)(000s)    Raw $    205 $    167    Purch Parts $    148 $    151    WIP $    389 $    322    Fin. Goods $    242 $    243TOTAL INVEN $    984 $    883 NOTES ON INVENTORIES AND MATERIAL MOVEMENTEMC does not account for inventories on a product line basis. But generally, each product line uses its proportionate share of the inventories based on costs.Plastic resin is moved to the molding machines where it is dumped into feeding hoppers for each machine. As the hopper empties, additional resin is dumped in.The plastic parts come out of the molding machines and are trimmed where they are collected in 10 cu. ft. tubs. These tubs are moved to the Plasti-Brack assembly area.The plain brackets are stamped out by the progressive dies in the Plasti-Brack press machine group. They are also collected in 10 cu. ft. tubs and then moved to the Plasti-Brack assembly area.In the assembly process, the operator will do a quick visual check of the plastic insert and the plain bracket before assembly. Bad parts are discarded into tubs. The plastic is recycled via a regrind process. The steel parts cannot be used again and sold for scrap with the rest of the scrap metal.The assembled Plasti-Brack items are collected in 10 cu. ft. tubs and are eventually moved to the Bulk Pack area. Once they are packed, they  move into the Finished Goods Warehouse where they wait to be picked and packed in large shipping containers to the customers. CAPACITY & FORECASTINGOverall, the current capacity utilization at EMC is 92%. This ranges from about 75% in the blanking machine groups to about 93% in the plastic molding groups. Assembly, packaging and packing are near 80%, while the finishing processes are around 88%.Currently, all departments are running just one 40 hour shift. Occasionally, some departments will add some overtime on a weekly basis as needed to stay up with orders. Bill Morton, the Plant Manager, prefers to run with one shift. His opinion is that adding a second shift is not as efficient since it adds more fixed costs in energy consumption, just to have the lights on. Additional shifts require additional employees. It costs money to hire and train them. Plus employees earn a 15% shift premium. Morton would rather pay the time & a half for the additional hours over 40. And Morton would prefer that his capacity utilization be around 85%. He is a little nervous with the 92% level.Mike Finch does the forecasting for EMC, both short-term and long-term. His short-term forecast is broken down by product line. His short-term forecast for Plasti-Brack products indicates that there will be a small increase this year of 7% to 10%.Finch's long term forecast is across the board for all of EMC and its various products. His results indicate that there will be a 12.5% annual compound growth over the next five years. This equates to an 80% increase over the current demand in the fifth year.Products: Construction and building items:FASTENERSscrews, bolts, nailsCONSTRUCTIONFlangesBrackets – Plasti-Brack (see below for more details)CABINET HARDWAREHingesKnobsPulls DECORATIVE HARDWARETowel BarsTowel RingsSoap DishesSwitch PlatesOutlet Plates 100 Heading101 small headers105 large headers150 Blanking & Stamping 151 small presses153 Bracket presses157 large presses200 Zinc Die Cast Molding & Trimming201 small zinc molders203 trim, small  206 large zinc molders208 trim,large   250 Plastic Injection Molding251 Plasti-brack insert molding253 Hinge insert molding255 Soap dish molding300 Plating301 Barrel Plating – nickel303 Barrel Plating – chromium305 Rack Plating330 Brushing331 Straight line brushing333 Circular line brushing360 Lacquer361 Spray lacquer line363 Brush lacquer line390 Painting391 Paint line 1393 Paint line 2395 Paint booth400 Assembly401 Hinge Assembly402 Hinge Assembly - auto403 Plasti-brack Assembly404 Towel Ring Assembly406 Soap Dish Assembly500 Packaging501 Bag Packaging503 Bar, Ring, Dish Packaging700 Packing701 Bulk Packing The Plasti-Brack Product Line: combination metal / plastic supportsSix products, different angles. F90, F100, F120A, F120B, F130, F135Novel item patented by ExcellentUnique design includes a simulated wood finish and color in the plastic insertAllows it to be used both for internal and external constructionVery popular in deck, fence, and shed construction, as well as in home construction.SAMPLE DRAWING & SAMPLE PROCESS FLOW CHARTFigure 1 shows a sample drawing of the F90. The P90 is the plastic insert, the S90 is the steel bracket and the F90 is the assembly of the P90 and S90. Figure 2 shows the process flow chart for the B-F90, which is the bulk packed F90.Mach hrs: hours for all machines in a production area
PPM: People per machine, e.g. how many people to run a machine, e.g. 0.5 means that one person runs two machines
People hrs: hours for all people in a production areaProduction: Hours producing pieces
Setup: Hours changing over or setting up dies
Pd Non-Prod: Hours paid doing non-production work (not producing pcs), e.g. maintenance, clean-up, etc.  ProductionSetupPd non-ProdTotal Mach HrsTotal Ppl HrsBlankingMach hrs33374672234027 ...PPM0.511  People hrs1668.5467223 2,358.50       MoldingMach hrs41957122505157 ...PPM0.2511  People hrs1048.75712250 2,010.75       AssemblyMach hrs333720105034422 ...PPM111  People hrs3337201050 34,422.00       PackingMach hrs667050717 ...PPM333  People hrs20010150 2,151.00       Total hrs    44,323.0040,942.25       Total Plasti-Brack Pcs       16,018,752Total Ppl Hours         40,942.25Productivity MeasurePcs produced/Ppl Hr           391.25Productivity Goal       105%         410.81 QUALITY MANAGEMENT EMC has not had a quality manager or quality department. One has just been hired to develop a Quality Department.The process operators have taken quality seriously on their own. They make sure that the tools and work stations are setup correctly. They also check the quality of parts periodically as they are produced. But they do not follow any specific quality methods or techniques. This approach to quality is the same in all of the various production departments.The majority of the production quality issues seems to be scrapping bad plastic inserts during the assembly process. A lot of 10 cu. ft. tubs accumulate in Plasti-Brack assembly. But no one seems to be concerned since these parts are very low cost and the plastic scrap is re-processed. Plastic scrap goes to a re-grind operation, where it is ground up into fine pieces. It is then added to the virgin raw material in a 1 to 9 ratio in the Plastic Injection Molding Department.Overall Excellent Manufacturing does not have many big issues from customer complaints. There are occasional returns of various products, mostly because of plating and finishing problems. In terms of Plasti-Brack products, complaints are about the plastic insert falling out and about sharp edges on the brackets. Last year there were 56 complaints complaints. They seem to be on the rise as there are 49 complaints this year during the first four months.PROCESSESMachine group 153 Bracket presses.Two 400-ton pressesmachine speed is 40 strokes per minute, or 2400 pieces per hourProgressive die process, so that one bracket part is produced per strokeSix progressive dies, one for each part.setup (die change over), approx. 3.5 hoursMachine group 251 Plasti-Brack insert MoldFour 250-ton plastic injection molding machinesThere are six dies, one for each plastic insertCavities per dieP90 die        6 cavitiesP100 die      5 cavitiesP120A die    8 cavitiesP120B die    4 cavitiesP130 die      7 cavitiesP135 die      8 cavitiesMachine speeds: Plastic injection molding speed is from 18 - 22 seconds/shotsee table below for Pieces/hr.Setup (die change over), approx. 4 hoursMachine group 403 Plasti-Brack AssemblySeven assembly stations – tables for operatorsOne operator per stationThe rate for the manual assembly operation is 8 pieces per minute or 480 pieces per hourThe assembly process consists of:grasp a plastic insert (P90)visually inspect insertif defective, toss into scrap bin and go to step 1, ORkeep for next stepgrasp a bracket (S90)move the insert to the assembly pointpush insert into placecheck assemblyif insert will not assemble properly, toss into scrap bin, go to steps 1, 2, 4, & 5, ORif insert does assemble properly, thendrop assembly into 10 cu. ft. Tub at the side of the table. Operators are trained to also do Hinge Assembly, Towel Bar, Towel Ring and Soap Dish assembly Machine group 701 Bulk PackingThree operators work together on this linePlasti-bracks move here from 403 Plasti-Brack AssemblyEach Plasti-brack is dumped in bulk into a cardboard boxEach box holds 100 of one of the items.Measuring the number in the box is accomplished by “weigh counting”A lid assembled to the full boxA label is attached to the boxThe closed container is banded by a banding machine on the conveyer lineThe completed container is sent to the warehouseThe speed of this line is 4 containers per minute (400 pieces/min.), or 240 containers/hour (24000 pieces/hr.)NOTE: Hinges are also “bare” bulk packed for cabinet makers. Otherwise hinges are bag packed first, then bulk packed to be sent to home supply stores.   MACH. GRP. 251        PIECES PER HOUR      M101           M102          M103            M104P1351309.11600.01440.01440.0P120A1309.11600.01440.01440.0P1300.01260.01145.51145.5P100818.20.0900.0900.0P901080.01350.01200.01200.0P120B640.0800.0720.0720.0MATERIAL HANDLING DATA:
PIECES PER 10 CU. FT. TUBP1351937 F1351191P120A1581 F120A1030P1301678 F1301075P1001305 F100891P901369 F90924P120B816 F120B609 Privacy Policy | Contact

Complex Problem

Question # 00061483 Posted By: solutionshere Updated on: 04/16/2015 06:03 AM Due on: 04/16/2015
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

We have begun to experience a growing backlog of customer orders in the Plasti-Brack product line.

For the last two to three months apparently we have had a slow creep-up of order backlog in the MLD250 department, specifically the Plasti-Brack molding group. It seems that we now have a 5 to 6 week backlog which is entirely unacceptable to our customers. As you know, our customers have been accustomed to getting orders shipped almost immediately or within a week of placing their orders. So now they don’t like to have to wait. Jack Walker and I think that this could possibly adversely affect our business since these items are so popular.

It is my opinion that we need more capacity in Machine Group 251. As you know, we have four 250-Ton plastic injection molding machines, which run these six parts. However, lately one of the machines seems to be experiencing excessive downtime. There also seems to be some tool wear causing low productivity. I suggest you talk to Don Stump to get more details on the order backlog and his scheduling system. Talk to Tom Gunner in Engineering or one of his Manufacturing Engineers about the machines and tools. And you should also check with Bill Morton and someone in the Plastic Injection Molding area about the tools. And while you are talking with Bill, ask him about his opinion of capacity. Ask Don Stump his opinion as well.

What I expect you to do consists of three main activities: 1) check out our capacity problem. See what we need to do to increase capacity. There is a capital budget available for the MLD2500 group - see Harvey Lund for more details. 2) We have to get our delivery time down to acceptable levels - see Don Stump for the details. 3) And while you are at, see what you can do to improve productivity and lower our costs. I expect your report in about two weeks with your recommendations and justification.

NEW INFORMATION GATHERED

There is a high reject rate of plastic inserts coming from MG 251, as found in the Plastic-Brack Assy, MG403 – it seems to be somewhere between 12% to 20% reject rate, depending on which plastic insert.

You also discover that the molding dies are very old and some of the mold cavities are closed off because of previous poor quality, which further reduces the yield rates from the standard expectations. Dies for P90, P120B, and P135 each have one cavity closed off. Swenson thinks that more should be closed off, based on his expertise and the age of these dies.

New plastic injection molding dies cost $25,000 each, or $30,000 each if they are designed for quick changeover. The lead time for manufacturing these dies by an outside tool and die company is 6 weeks each.

One of the four molding machines, M101, has a record of high unscheduled repair and downtime. It seems to need some minor adjustments several times per week, which is causing low uptime for it. Swenson, the molding supervisor, would like to see the machine have a complete overhaul. Dick Wrangle would like to purchase a new 250-ton molding machine. The cost to overhaul is estimated to $100,000, and the cost of a new machine is $250,000.

Mark Monnin, the Purchasing Manager, tells you that there is better grade plastic resin that could be used, but it is more expensive. The better materials are RP515 at $0.28 per pound or RP625 at $0.30 per pound; the current material in use is RP502 at $0.26 per pound; the quality ranking order is RP625 > RP515 > RP502. Monnin believes the best material, RP625, would reduce some of the scrapped parts generated by MG251. He is not sure how RP515 would do.

Bill Morton, the Plant Manager, informs you that a second shift has not been approved at this time, but could be as a last resort. There is a 15% shift premium paid to those who work on the 2nd shift. Overtime could also be used, possibly 2 extra hours per day and up to 10 hours on Saturdays. OT earns employees an additional half-time for hours over 40 per week.

The setup times (die changeover) in both blanking and molding are in the three and half to four and a half hour range. You asked Tom Tucker what it would take to modify these dies with quick clamps and other mechanisms so that you could reduce the setup times. Tucker said that to modify existing dies would cost about $10,000 each. Your research in this area confirms this number is in the ballpark and that setup times can be reduced to about 0.5 to 1.0 hours.

Harvey Lund indicates that there is a capital budget for MLD250, of which $325,000 is available for MLD251. You can purchase machines, tools, overhauls and tool upgrades with this budget. He also says that you don’t need to spend all of it.

Mike Finch, the Marketing Analyst, says that the demand rate of customer orders has not increased substantially in the last quarter, nor does he think that it is going to rise much soon. He still stands by his long term forecast over the next five years.

Assignment

Analyze the situation in the Plasti-brack product line. Diagnose the problem and possible solutions to the capacity and order backlog. Determine an appropriate plan for correcting the problem. Justify your plan and make recommendations using your knowledge of productivity, process improvement, inventory, capacity, forecasting, and quality. Write a report to the VP of Operations.

Expectations

· Explore the possibilities of spending some of the capital budget on a machines and or tools. Also consider improving setup time, improving quality, increasing capacity, and determining EOQs.

· Determine a plan for solving this problem in the Plasti-brack product line. Consider there may be both a short-term solution and a long-term solution.

· Justify your plan based on the concepts of capacity management.

The following is the Income Statement from the year just completed.

Gross Income

COGS

Gross Margin

PRODUCT LINE

(000s)

(000s)

(000s)

Fasteners

$ 1,010

7.3%

$ 646

4.7%

$ 364

2.6%

Cabinet Hardware

$ 3,243

23.5%

$ 1,783

12.9%

$ 1,460

10.6%

Construction Hardware

$ 4,165

30.2%

$ 1,874

13.6%

$ 2,291

16.6%

Decorative Hardware

$ 5,388

39.0%

$ 2,586

18.7%

$ 2,802

20.3%

TOTALS

$ 13,806

100.0%

$ 6,889

49.9%

$ 6,917

50.1%

OPERATING EXPENSES

Marketing and Advertising

$ 850

6.2%

Commissions, Wages & Salaries

$ 1,750

12.7%

Benefits

$ 770

5.6%

Office Expenses

$ 175

1.3%

Depreciation

$ 734

5.3%

Insurance

$ 943

6.8%

Fixed Energy & Utility Expenses

$ 268

1.9%

Miscellaneous

$ 132

1.0%

TOTAL OPERATING EXPENSES

$ 5,622

40.7%

Net Income Before Taxes

$ 1,295

9.4%

The following is the Statement of Inventories (from the Balance Sheet) for the year just ending:

Beginning

Ending

Inventories

(000s)

(000s)

Raw

$ 205

$ 167

Purch Parts

$ 148

$ 151

WIP

$ 389

$ 322

Fin. Goods

$ 242

$ 243

TOTAL INVEN

$ 984

$ 883

NOTES ON INVENTORIES AND MATERIAL MOVEMENT

EMC does not account for inventories on a product line basis. But generally, each product line uses its proportionate share of the inventories based on costs.

Plastic resin is moved to the molding machines where it is dumped into feeding hoppers for each machine. As the hopper empties, additional resin is dumped in.

The plastic parts come out of the molding machines and are trimmed where they are collected in 10 cu. ft. tubs. These tubs are moved to the Plasti-Brack assembly area.

The plain brackets are stamped out by the progressive dies in the Plasti-Brack press machine group. They are also collected in 10 cu. ft. tubs and then moved to the Plasti-Brack assembly area.

In the assembly process, the operator will do a quick visual check of the plastic insert and the plain bracket before assembly. Bad parts are discarded into tubs. The plastic is recycled via a regrind process. The steel parts cannot be used again and sold for scrap with the rest of the scrap metal.

The assembled Plasti-Brack items are collected in 10 cu. ft. tubs and are eventually moved to the Bulk Pack area. Once they are packed, they move into the Finished Goods Warehouse where they wait to be picked and packed in large shipping containers to the customers.

CAPACITY & FORECASTING

Overall, the current capacity utilization at EMC is 92%. This ranges from about 75% in the blanking machine groups to about 93% in the plastic molding groups. Assembly, packaging and packing are near 80%, while the finishing processes are around 88%.

Currently, all departments are running just one 40 hour shift. Occasionally, some departments will add some overtime on a weekly basis as needed to stay up with orders. Bill Morton, the Plant Manager, prefers to run with one shift. His opinion is that adding a second shift is not as efficient since it adds more fixed costs in energy consumption, just to have the lights on. Additional shifts require additional employees. It costs money to hire and train them. Plus employees earn a 15% shift premium. Morton would rather pay the time & a half for the additional hours over 40. And Morton would prefer that his capacity utilization be around 85%. He is a little nervous with the 92% level.

Mike Finch does the forecasting for EMC, both short-term and long-term. His short-term forecast is broken down by product line. His short-term forecast for Plasti-Brack products indicates that there will be a small increase this year of 7% to 10%.

Finch's long term forecast is across the board for all of EMC and its various products. His results indicate that there will be a 12.5% annual compound growth over the next five years. This equates to an 80% increase over the current demand in the fifth year.

Products: Construction and building items:

• FASTENERS

? screws, bolts, nails

• CONSTRUCTION

? Flanges

? Brackets – Plasti-Brack (see below for more details)

• CABINET HARDWARE

? Hinges

? Knobs

? Pulls

• DECORATIVE HARDWARE

? Towel Bars

? Towel Rings

? Soap Dishes

? Switch Plates

Outlet Plates

• 100 Heading

? 101 small headers

? 105 large headers

• 150 Blanking & Stamping

? 151 small presses

? 153 Bracket presses

? 157 large presses

• 200 Zinc Die Cast Molding & Trimming

? 201 small zinc molders

? 203 trim, small

? 206 large zinc molders

? 208 trim,large

• 250 Plastic Injection Molding

? 251 Plasti-brack insert molding

? 253 Hinge insert molding

? 255 Soap dish molding

• 300 Plating

? 301 Barrel Plating – nickel

? 303 Barrel Plating – chromium

? 305 Rack Plating

• 330 Brushing

? 331 Straight line brushing

? 333 Circular line brushing

• 360 Lacquer

? 361 Spray lacquer line

? 363 Brush lacquer line

• 390 Painting

? 391 Paint line 1

? 393 Paint line 2

? 395 Paint booth

• 400 Assembly

? 401 Hinge Assembly

? 402 Hinge Assembly - auto

? 403 Plasti-brack Assembly

? 404 Towel Ring Assembly

? 406 Soap Dish Assembly

• 500 Packaging

? 501 Bag Packaging

? 503 Bar, Ring, Dish Packaging

• 700 Packing

? 701 Bulk Packing

The Plasti-Brack Product Line: combination metal / plastic supports

• Six products, different angles. F90, F100, F120A, F120B, F130, F135

• Novel item patented by Excellent

• Unique design includes a simulated wood finish and color in the plastic insert

• Allows it to be used both for internal and external construction

• Very popular in deck, fence, and shed construction, as well as in home construction.

SAMPLE DRAWING & SAMPLE PROCESS FLOW CHART

Figure 1 shows a sample drawing of the F90. The P90 is the plastic insert, the S90 is the steel bracket and the F90 is the assembly of the P90 and S90. Figure 2 shows the process flow chart for the B-F90, which is the bulk packed F90.

Dot Image
Tutorials for this Question
  1. Tutorial # 00057403 Posted By: solutionshere Posted on: 04/16/2015 06:05 AM
    Puchased By: 3
    Tutorial Preview
    packers are required per machine. constraints EMC has two types ...
    Attachments
    1430011.docx (60.3 KB)
Whatsapp Lisa