Project Management-Project Management Lesson 4 Graded Problem Set

Question # 00291658 Posted By: kimwood Updated on: 05/21/2016 05:32 AM Due on: 06/20/2016
Subject Business Topic General Business Tutorials:
Question
Dot Image
B ADM: Project Management
Lesson 4 Graded Problem Set
Please complete all graded problems. This assignment is open book and open notes; however, you may NOT help or
share answers with your fellow team members or classmates. You do not have a time limit.
All answers must be submitted using the “answer submission form.” You will only be allowed one-time access to the
submission form (so have your answers ready!). Once started the submission form will only be open for 1 hour.
NO offline or e-mail submissions will be accepted.
Use the project network, baseline time-phase budget and status information below to answer questions in this problem set.

Baseline (PV)
DUR

ES

SL

Budget
(PV)

A

2

0

2

0

100

B

3

2

5

0

200

50

C

1

2

6

3

200

200

D

2

2

5

1

200

150

E

1

5

6

0

100

F

2

4

7

1

600

G

3

6

10

1

600

200

100

300

H

4

6

10

0

800

200

200

200

I

3

6

10

1

600

100

400

100

J

2

10

12

0

600

Task

LF

0

1
25

2

3

4

5

6

7

8

9

10

11

75
100

50

50
100
300

300
200
300

300

Period PV Total

25

75

400

150

350

400

500

700

600

200

300

300

Cumulative PV Total

25

100

500

650

1000

1400

1900

2600

3200

3400

3700

4000

12

Section I
Based on the data provided in the Period 4 Status Report below answer the questions in this section.
Status Report Ending Period 4
Task

% Complete

EV

AC

PV

A

100%
50%

80

C

75%

100

D

50%

125

E

0%

0

F

0%

0

G

0%

0

H

0%

0

I

0%

0

J

0%

SV

150

B

CV

0

1.
2.
3.
4.

After period 4, what is the Planned Value (PV) of the worked schedule for Task A (round answer to two decimal places)? (5
pts.)
After period 4, what is the Earned Value (EV) for Task D (round answer to two decimal places)? (5 pts.)
After period 4, what is the Cost Variance (CV) for Task B (round answer to two decimal places)? (5 pts.)
After period 4, what is the Schedule Variance (SV) for Task C (round answer to two decimal places)? (5 pts.)

Section II
Based on the data provided in the Period 8 Status Report below answer the questions in this section.
Status Report Ending Period 8

Task % Complete EV
AC
PV
CV
SV
A
100%
100 150 100
-50
0
B
100%
200 140 200
60
0
C
100%
200 110 200
90
0
D
100%
200 260 200
-60
0
E
100%
100 120 100
-20
0
F
100%
600 520 600
80
0
G
100%
600 700 300 -100
300
H
45%
360 100 400
260
-40
I
15%
90 100 500
-10
-410
J
0%
0
0
0
0
0
Cumulative Totals
2450 2200 2600
250
-150
5.
6.
7.

After period 8, what is the Scheduling Performance Index (SPI) value (round answer to two decimal places)? (5 pts.)
After period 8, what is the Cost Performance Index (CPI) value (round answer to two decimal places)? (5 pts.)
After period 8, what is the Percent Complete Index based on Budget Amounts (PCI-B) (ro round answer to two decimal
places)? (5 pts.)
8. After period 8, what is the To Complete Performance Index (TCPI) (round answer to two decimal places)? (5 pts.)
9. After period 8, what is the forecasted Estimated Total Cost at Completion (EACf) (r round answer to two decimal places)?
(5 pts.) (Hint: use the forecasting method)
10. After period 8, what is the forecasted Variance at Completion (VACf) (round answer to two decimal places)? (5 pts.) (Hint:
use the forecasting method)

Section III
You have been provided with the following revised estimates for the remainder of the project:
Activity H will be completed at the end of period 12 at a total cost of 600
Activity I will be completed at the end of period 12 at a total cost of 750
Activity J will be completed at the end of period 14 at a total cost of 500
Use the above revised estimates to answer the questions in this section.
11. Base on the revised estimates, what is the Estimated Total Cost at Completion (EACre) (round answer to two decimal
places)? (5 pts.) (Hint: use the revised estimate method)
12. Base on the revised estimates, what is the Variance at Completion (VACre) (round answer to two decimal places)? (5 pts.)
(Hint: use the revised estimate method)

Section IV
Use the information provided below to compress one time unit per move using the least cost method. Reduce the schedule until you
reach the crash point of the network.

CODE
ES Early Start
EF Early Finish
LS Late Start
LF Late Finish
SL Slack
ID Activity Identifier
DUR Duration

0

EF

ID

LS

DUR

4

4
6

4

10

8

18

13

13

G

18

18

0

0

0

0

13

18

18

11

11

0

0

11

11

2

13

5

11

E

6

4

11

15

4

A

6
5

F

12
6

14

C

0

6

LF

4

4

0

Critical Path – “BCDGH”

SL

SL

0

B

0
0

ES

7

D

5

H

0
6

4
3

18

Figure 1

Activity ID

Activity
Predecessor

Table 2
Crash
Max
Cost
Crash
(Slope)
Time

Normal
Cost

Normal
Time
(days)

A

None

125

2

2000

5

B

None

225

2

4000

4

C

B

150

3

2500

7

D

A, C

50

1

1000

2

E

A, C

--

0

5000

3

F

B

300

3

3000

8

G

D

100

2

500

5

H

E, F, G

200

3

1000

24

6

13. What is the direct cost of the project after the project is crashed using the least cost method to duration of 18 days (round
answer to two decimal places)? (5 pts.)
14. Which activities do you need to crash to get to the crash point of the network? (5 pts.)
15. What is the duration (in days) of the project after the project is crashed to the crash point of the network? (10 pts.)

24

Section V
Table 3 below provides the direct and indirect costs incurred by an IT project for various project durations. Use this information to
answer the questions in this section.
Table 3
Project
Duration
(in days)
57

Direct Costs
3200

Indirect
Cost
1100

54

3400

1050

50

3550

1000

48

3850

950

16. Given the data provided in Table 3, should the project be crashed? (5 pt.)
17. If the project’s client was willing to pay $100 for each day the project was delivered early to the 48th day mark, what day
would you crash the project to? (5 pts.)
Section VI
Use the information provided below to answer the question in this section.
Assume your project team has identified two factors that significantly affect the project’s probability of failure, degree of integration
(Pi) and number of units involved (P n); where the probability of Pi and Pn are 0.30 and 0.45, respectively. They have also identified the
following five consequences: time (Ct), budget (Cb), quality (Cq), external stakeholder satisfaction (Ce), and internal stakeholder
satisfaction (Ci). They have determined the value of these consequences as follows: Ct= 0.20, Cb= 0.40, Cq= 0.30, Ce= 0.30, and Ci =
0.10.
18. Based on a calculated risk factor (RF), how would you classify the risk (Low RF < 0.30, Medium RF 0.30 to 0.70, High RF >
0.70)? (10 pts.)
Dot Image
Tutorials for this Question
  1. Tutorial # 00286976 Posted By: kimwood Posted on: 05/21/2016 05:32 AM
    Puchased By: 3
    Tutorial Preview
    the project after the project is crashed using the least ...
    Attachments
    Lesson_4_Graded_Problem_Set.docx (28.67 KB)

Great! We have found the solution of this question!

Whatsapp Lisa