Project Management-PROJ 592-Activity A is 60% complete at a cost so far of $50,000.

Question # 00285287 Posted By: kimwood Updated on: 05/15/2016 06:13 PM Due on: 06/14/2016
Subject Business Topic General Business Tutorials:
Question
Dot Image

Question 1:-

Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project’s ETC.

Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It is at the end of Week 3 of 5. Activity B is 85% complete at a cost so far of $150,000. It was estimated to cost $80,000 when finished. It is at the end of Week 4 of 5. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 when finished. Assume spending will continue at the same rate.


Question 2

You are the project manager assigned to oversee the installation of an online professional development system. This is an off the shelf package which is expected to take 120 days to complete. The total cost per day is $2,666. After 75 days the project is 61% complete and $230,000 has been spent. What is the estimate to complete (ETC). Is the project over budget or under budget?

Dot Image
Tutorials for this Question
  1. Tutorial # 00280574 Posted By: kimwood Posted on: 05/15/2016 06:13 PM
    Puchased By: 3
    Tutorial Preview
    manager assigned to oversee the ...
    Attachments
    Activity_A_budget_at_completion.docx (11.71 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    amart...il.com Rating Supreme quality work 09/27/2016

Great! We have found the solution of this question!

Whatsapp Lisa