PROJECT 1 Determine the unconstrained critical path and its length

Question # 00323392 Posted By: rey_writer Updated on: 06/24/2016 07:33 AM Due on: 06/24/2016
Subject Business Topic Management Tutorials:
Question
Dot Image
ActivityImmediate PredecessorDuration in days (unconstrained at 8-hours per day)ResourceHourly costAvailable
Work Hours per Day (constrained)
AEvaluate freezers2Alcides$456
BChart temperatures6Joan$504
CReview service record2Alcides
DConsult with HVAC engineerA,B,C3Alcides
EDevelop construction planD10Joan
FComplete IC assignmentE2Alcides
GComplete ROI analysisE5Joan
HConduct regulatory reviewE4Joan
IObtain construction approvalF,G,H2Alcides

Question 3

WBSActivityImmediate Predecessor

Duration in weeks (unconstrained at 8-hours per day)

ResourceHourly costAvailable
Hours per week (constrained)
1Operational definition
1.1Research literature3Becky$3530
1.2Identify and define terms1.11Ann$6030
1.3Obtain approval of definition1.22Clive$5020
2Target Selection
2.1Solicit partners for pilot2Ann
2.2Hold brainstorming meeting2.12Becky
2.3Identify characteristics of targets2.2, 3.11Ann
2.4Obtain approval of partners2.3, 1.2, 3.41Clive
3Question set
3.1Identify process group members2Clive
3.2Develop question set2.34Ann
3.3Prototype and validate question set3.23Becky
3.4Add partners3.1, 2.13Becky
4Pilot process
4.1Schedule with target audience2.42Becky
4.2Conduct beta test3.4, 2.42Clive
4.3Process feedback from target audience4.22Ann
4.4Conduct pilot4.32Clive
4.5Analyze results4.42Clive

Respond to the following questions:

  1. Determine the unconstrained critical path and its length (use days for Question 2, use weeks for question 3; use project days only, no weekends).
  2. Determine the total hours and the hours per person required to complete the work?
  3. Determine the total labor cost and the labor cost per person?
  4. Prepare a Gantt chart illustrating the project length using constrained resource assignments and illustrating logical precedence diagramming for each activity (e.g., show finish-start relationships). Include color-coding by resource for each bar of the Gantt chart.
  5. Develop a responsibility histogram for each resource over the length of the project and describe what adjustments, if any, were made to the project schedule to effectively deal with resource overloads or other schedule conflicts related to precedence (logic) requirements
  6. Prepare a resourced-constrained (yet resource-leveled) critical path and its length.
  7. Prepare a figure similar to Exhibit 9.9 (CPM) illustrating a cumulative cost curve.
Dot Image
Tutorials for this Question
  1. Tutorial # 00318958 Posted By: rey_writer Posted on: 06/24/2016 07:33 AM
    Puchased By: 3
    Tutorial Preview
    The solution of PROJECT 1 Determine the unconstrained critical path and its length...
    Attachments
    IMG_1093.zip (0.12 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    sh...cook Rating Provide assignments on time 11/19/2017

Great! We have found the solution of this question!

Whatsapp Lisa