One of PLEs manufacturing facilities produces metal
One of PLEs manufacturing facilities produces metal engine housings from sheet metal for both mowers and tractors. Production of each product consists of five steps: stamping, drilling, assembly, painting, and packaging to ship to its final assembly plant. The production rates in hours per unit and the number of production hours available in each department are given in the following table:
|
Department |
Mower Housings |
Tractor Housings |
Production Hours available |
|
Stamping |
0.03 |
0.07 |
200 |
|
Drilling |
0.09 |
0.06 |
300 |
|
Assembly |
0.15 |
0.10 |
300 |
|
Painting |
0.04 |
0.06 |
220 |
|
Packaging |
0.02 |
0.04 |
100 |
In addition:
· Mower housings require 1.2 square feet of sheet metal per unit
· Tractor housings require 1.8 square feet of sheet metal per unit
· 2500 square feet of sheet metal is available.
The company would like to maximize the total number of housings they can produce during the planning period.
Formulate and solve a linear optimization model using Solver, and recommend a production plan. Conduct whatever what-if analyses(run different scenarios and apply parameter analysis) you feel are appropriate to include.
-