A project to remodel a garage has the following activities
Question # 00277512
Posted By:
Updated on: 05/07/2016 12:47 PM Due on: 06/06/2016
A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
ActivityDurationPredecessors
A4 months---
B3 months---
C3 months---
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
- What are the critical path activities?
- What is the project's scheduled completion time?
- What is the slack or float for Activity C? Show your calculations.
- What is the slack or float for Activity D? Show your calculations.
- What is the slack or float for Activity F? Show your calculations.
-