UCM CIS 5675 The following project is at the end of its first week. Find the cost and schedule variances
- The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.
Task | Predecessors | Duration in days | Planned Value ($) | Actual Cost ($) | Percent Complete |
A | None | 2 | 500 | 650 | 100 |
B | None | 3 | 1000 | 1500 | 100 |
C | A | 2 | 200 | 300 | 50 |
D | A | 5 | 600 | 600 | 20 |
E | B ,C | 6 | 1200 | 550 | 10 |
To do this exercise, it is best to start with a Gantt chart depicting the task relationships.
CV ______________________ CPI ________________
SV ______________________ SPI ________________
EAC _____________________
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
- Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c
Planned value: 6700
Earned value: 6100
Actual costs: 7300
Budget at completion: 38900
CPI _______________________ SPI _____________________________
EAC ______________________
------------------------------------------------------------------------------------------------------------------------------------------------------------------------
- The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.
Task | Predecessors | Duration in days | Planned Value ($) | Actual Cost ($) | Percent Complete |
A | None | 3 | 600 | 650 | 100 |
B | A | 5 | 1000 | 1500 | 100 |
C | A | 2 | 200 | 300 | 100 |
D | A | 5 | 1000 | 600 | 100 |
E | B ,C | 6 | 1200 | 1200 | 100 |
F | C | 10 | 10000 | 12000 | 75 |
G | F | 7 | 700 | 0 | 0 |
H | G | 8 | 1600 | 0 | 0 |
To do this exercise, it is best to start with a Gantt chart depicting the task relationships.
CV ______________________ CPI ________________
SV ______________________ SPI ________________
EAC _____________________
-
Rating:
/5
Solution: UCM CIS 5675 The following project is at the end of its first week. Find the cost and schedule variances