UCM CIS 5675 The following project is at the end of its first week. Find the cost and schedule variances

Question # 00277463 Posted By: kimwood Updated on: 05/07/2016 12:47 PM Due on: 06/06/2016
Subject Business Topic Management Tutorials:
Question
Dot Image
  • The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________ CPI ________________

SV ______________________ SPI ________________

EAC _____________________

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

  • Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________ SPI _____________________________

EAC ______________________

------------------------------------------------------------------------------------------------------------------------------------------------------------------------

  • The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

600

650

100

B

A

5

1000

1500

100

C

A

2

200

300

100

D

A

5

1000

600

100

E

B ,C

6

1200

1200

100

F

C

10

10000

12000

75

G

F

7

700

0

0

H

G

8

1600

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________ CPI ________________

SV ______________________ SPI ________________

EAC _____________________

Dot Image
Tutorials for this Question
  1. Tutorial # 00272722 Posted By: kimwood Posted on: 05/07/2016 12:47 PM
    Puchased By: 3
    Tutorial Preview
    value: 6700Earned value: 6100Actual costs: 7300...
    Attachments
    docx.docx (18.16 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    mig...se85 Rating Good-quality and satisfactory content 09/22/2016

Great! We have found the solution of this question!

Whatsapp Lisa