Attachment # 00002350 - Case_Problem_7.docx
Case_Problem_7.docx (27.68 KB)
Raw Preview of Attachment:
(refer to the detailed question and attachment below)
13-1 NPV with Normal Cash Flows. Compute the NPV for Project M and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. (LG13-3)Project MTime:012345Cash flow-$1,000$350$480$520$600$10012-2 PV of Depreciation Tax Benefits. Your company is considering a new project that will require $1 million of new equipment at the start of the project. The equipment will have a depreciable life of 10 years and will be depreciated to a book value of $150,000 using straight-line depreciation. The cost of capital is 13 percent, and the firm’s tax rate is 34 percent. Estimate the present value of the tax benefits from depreciation. (LG12-4) 13-3 NPV with Non-Normal Cash Flows. Compute the NPV statistic for Project U and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. (LG13-3)Project UTime:012345Cash flow-$1,000$350$1,480$520$300-$10013-4 NPV with Non-Normal Cash Flows. Compute the NPV statistic for Project K and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. (LG13-3)Project KTime:012345Cash flow-$10,000$5,000$6,000$6,000$5,000-$10,00013-5 Payback. Compute the payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable payback is 3 years. (LG13-2)Project BTime:012345Cash flow-$11,000$3,350$4,180$1,520$0$1,00013-6 Payback. Compute the payback statistic for Project A and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable payback is 4 years. (LG13-2)Project ATime:012345Cash flow-$1,000$350$480$520$300$10013-7 Discounted Payback. Compute the discounted payback statistic for Project C and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback is 3 years. (LG13-2) Project CTime:012345Cash flow-$1,000$480$480$520$300$10013-8 Discounted Payback. Compute the discounted payback statistic for Project D and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 4 years. (LG13-2) Project DTime:012345Cash flow-$11,000$3,350$4,180$1,520$0$1,00013-13 PI. Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. (LG 13-6) Project ZTime:012345Cash flow-$1,000$350$480$650$300$10013-14 PI. Compute the PI statistic for Project Q and indicate whether you would accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. (LG 13-6) Project QTime:01234Cash flow-$11,000$3,350$4,180$1,520$2,000Use this information to answer the next four questions. If a particular decision method should not be used, indicate why.Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistics for the project are 3.5 and 4.5 years, respectively. Time:0123456Cash flow-$5,000$1,200$2,400$1,600$1,600$1,400$1,20013-17 Payback. Use the payback decision rule to evaluate this project; should it be accepted or rejected? (LG13-2)13-19 IRR. Use the IRR decision rule to evaluate this project; should it be accepted or rejected? (LG13-4)13-21 NPV. Use the NPV decision rule to evaluate this project; should it be accepted or rejected?(LG13-3) 13-22 PI. Use the PI decision rule to evaluate this project; should it be accepted or rejected?(LG13-6)Use this information to answer the next question. If you should not use a particular decision technique, indicate why.Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for the project are 3 and 3.5 years, respectively. Time:012345Cash flow-$235,000$68,800$84,000$141,000$122,000$81,20013-28 PI. Use the PI decision rule to evaluate this project; should it be accepted or rejected?(LG13-6)

Need Help solving finance homework problems

Question # 00034105 Posted By: garciavegaa Updated on: 11/30/2014 08:52 PM Due on: 12/02/2014
Subject Finance Topic Finance Tutorials:
Question
Dot Image

13-1 NPV with Normal Cash Flows. Compute the NPV for Project M and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. (LG13-3)

Project M

Time:

0

1

2

3

4

5

Cash flow

-$1,000

$350

$480

$520

$600

$100

12-2 PV of Depreciation Tax Benefits. Your company is considering a new project that will require $1 million of new equipment at the start of the project. The equipment will have a depreciable life of 10 years and will be depreciated to a book value of $150,000 using straight-line depreciation. The cost of capital is 13 percent, and the firm’s tax rate is 34 percent. Estimate the present value of the tax benefits from depreciation. (LG12-4)

13-3 NPV with Non-Normal Cash Flows. Compute the NPV statistic for Project U and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. (LG13-3)

Project U

Time:

0

1

2

3

4

5

Cash flow

-$1,000

$350

$1,480

$520

$300

-$100

13-4 NPV with Non-Normal Cash Flows. Compute the NPV statistic for Project K and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. (LG13-3)

Project K

Time:

0

1

2

3

4

5

Cash flow

-$10,000

$5,000

$6,000

$6,000

$5,000

-$10,000

13-5 Payback. Compute the payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable payback is 3 years. (LG13-2)

Project B

Time:

0

1

2

3

4

5

Cash flow

-$11,000

$3,350

$4,180

$1,520

$0

$1,000

13-6 Payback. Compute the payback statistic for Project A and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable payback is 4 years. (LG13-2)

Project A

Time:

0

1

2

3

4

5

Cash flow

-$1,000

$350

$480

$520

$300

$100

13-7 Discounted Payback. Compute the discounted payback statistic for Project C and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback is 3 years. (LG13-2)

Project C

Time:

0

1

2

3

4

5

Cash flow

-$1,000

$480

$480

$520

$300

$100

13-8 Discounted Payback. Compute the discounted payback statistic for Project D and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 4 years. (LG13-2)

Project D

Time:

0

1

2

3

4

5

Cash flow

-$11,000

$3,350

$4,180

$1,520

$0

$1,000

13-13 PI. Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. (LG 13-6)

Project Z

Time:

0

1

2

3

4

5

Cash flow

-$1,000

$350

$480

$650

$300

$100

13-14 PI. Compute the PI statistic for Project Q and indicate whether you would accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. (LG 13-6)

Project Q

Time:

0

1

2

3

4

Cash flow

-$11,000

$3,350

$4,180

$1,520

$2,000

Use this information to answer the next four questions. If a particular decision method should not be used, indicate why.

Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistics for the project are 3.5 and 4.5 years, respectively.

Time:

0

1

2

3

4

5

6

Cash flow

-$5,000

$1,200

$2,400

$1,600

$1,600

$1,400

$1,200

13-17 Payback. Use the payback decision rule to evaluate this project; should it be accepted or rejected? (LG13-2)

13-19 IRR. Use the IRR decision rule to evaluate this project; should it be accepted or rejected? (LG13-4)

13-21 NPV. Use the NPV decision rule to evaluate this project; should it be accepted or rejected?

(LG13-3)

13-22 PI. Use the PI decision rule to evaluate this project; should it be accepted or rejected?

(LG13-6)

Use this information to answer the next question. If you should not use a particular decision technique, indicate why.

Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for the project are 3 and 3.5 years, respectively.

Time:

0

1

2

3

4

5

Cash flow

-$235,000

$68,800

$84,000

$141,000

$122,000

$81,200

13-28 PI. Use the PI decision rule to evaluate this project; should it be accepted or rejected?

(LG13-6)

Dot Image
Tutorials for this Question
  1. Tutorial # 00033483 Posted By: neil2103 Posted on: 12/01/2014 12:48 AM
    Puchased By: 4
    Tutorial Preview
    The solution of CAse problems ch 7...
    Attachments
    Case_Problem_7.docx (165.55 KB)
Whatsapp Lisa