Exercise 10.3 Measures of Internal Business Process Performance - Mittel Rhein AG of Köln, Germany
|
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: |
|
|
|
|
|
Inspection time |
0.3 |
days |
|
Wait time (from order to start of production) |
14.0 |
days |
|
Process time |
2.7 |
days |
|
Move time |
1.0 |
days |
|
Queue time |
5.0 |
days |
|
|
|
Requirement 1: |
|
Compute the throughput time. |
|
Throughput time |
days |
|
Requirement 2: |
|
Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to 2 decimal places.) |
|
Manufacturing cycle efficiency |
|
|
Requirement 3: |
|
What percentage of the throughput time was spent in non-value-added activities? (Omit the "%" sign in your response.) |
|
Throughput time |
% |
|
Requirement 4: |
|
Compute the delivery cycle time. |
|
Delivery cycle time |
days |
|
Requirement 5: |
|
If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Round your answer to 3 decimal places.) |
|
Manufacturing cycle efficiency |
|
-
Rating:
/5
Solution: Exercise 10.3 Measures of Internal Business Process Performance - Mittel Rhein AG of Köln, Germany