Saint GBA334 Week 5 quiz 3

Question # 00026734 Posted By: mac123 Updated on: 09/25/2014 11:41 PM Due on: 09/30/2014
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image
1. Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks. The crash time for Activity A is 3 weeks and the crash cost is $600. What is the crash cost per week for Activity A? (Points : 3)





Question 2. 2. Considering the following Activity-On-Node (AON) project (activity completion times are in days), how long will it take to complete the project?

Activity-On-Node

Click here to view a Word version of the project.
(Points : 3)





Question 3. 3. Considering the following Activity-On-Node (AON) project (activity completion times are in days), what is the slack time associated with activity D?

Activity-On-Node

Click here to view a Word version of the project.
(Points : 3)





Question 4. 4. Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the standard deviation associated with the completion time of activity B?

Activity-On-Node-2

Click here to view a Word version of the project.
(Points : 3)





Question 5. 5. Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the expected completion time of activity A?

Activity-On-Node-2

Click here to view a Word version of the project.
(Points : 3)





Question 6. 6. Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B A
C A
D B, C
E B, C
F D, E
G F

Jamie was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 4
B 4
C 5
D 3
E 3
F 2
G 1

Considering the information above, what is the length of the project?
(Points : 3)





Question 7. 7. Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate
Activity
Predecessors
A -
B -
C A, B
D C
E C
F D, E
G E
H F, G


Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2

Considering the information above, what is the earliest finish time for activity F?
(Points : 3)





Question 8. 8. Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate
Activity
Predecessors
A -
B -
C A, B
D C
E C
F D, E
G E
H F, G


Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2

Considering the information above, what is the slack time for activities E and F respectively?
(Points : 3)





Question 9. 9. Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5

Considering the information above, what is the length of the project?
(Points : 3)





Question 10. 10. Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5

Considering the information above, what is the earliest finish time for activity E?
(Points : 3)



Dot Image
Tutorials for this Question
  1. Tutorial # 00026419 Posted By: mac123 Posted on: 09/28/2014 01:59 PM
    Puchased By: 47
    Tutorial Preview
    G E H F, G Also assume that the painters ...
    Attachments
    Multiple_Choice.docx (82.47 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    mik...369 Rating Excellent team support and best services 03/09/2018
    li...mie Rating Best quality tutorials 03/12/2018
    fl...ack Rating Tutorials are as per requirements 10/24/2016
    bc...nce Rating The work is of top and best quality 07/05/2016
    si...13 Rating Provide quick solutions to every problem 07/05/2016

Great! We have found the solution of this question!

Whatsapp Lisa