Question
1. 1.In a PERT network, the earliest (activity) start time is
the: (Points : 2)
earliest time that an activity can be finished without delaying the entire
project.
latest time that an activity can be started without delaying the entire
project.
earliest time that an
activity can start without violation of precedence requirements.
latest time that an activity can be finished without delaying the entire
project.
none of the above.
Question
2. 2.Given an activity's optimistic, most likely, and pessimistic
time estimates of 4, 12, and 18 days respectively, what is the PERT
variance for this activity? (Points : 2)
2.33
5.44
8.00
64.00
None of the above
Question
3. 3.The expected time in PERT is: (Points : 2)
a weighted average of
the most optimistic time, most pessimistic time, and four times the most
likely time.
the modal time of a beta distribution.
a simple average of the most optimistic, most likely, and most pessimistic
times.
the square root of the sum of the variances of the activities on the
critical path.
none of the above.
Question
4. 4.According to the table below, there are five activities in a
PERT project.
Click here to view
a Word version of the table.
Using the data in the table, if the normal distribution were used to find
the probability of finishing this project in 24 weeks or fewer, what mean
and variance respectively would be used?
(Points : 2)
Question
5. 5.The following table represents a project with four
activities. All times are in weeks.
Click here to view
a Word version of the table.
Using the data in the table, what is the critical path?
(Points : 2)
A-B
A-C
B-D
A-B-C-D
None of the above
Question
6. 6.Bank Boston has a branch at Bryant College. The branch is
busiest at the beginning of the college year when freshmen and transfer
students open accounts. This year, freshmen arrived at the office at a
rate of 40 per day (assume 8-hour days). On average, it takes the Bank
Boston staff person about ten minutes to process each account
application. The bank is considering having one or two tellers. Each
teller is paid $12 per hour and the cost of waiting in line is assumed to
be $8 per hour.
What is the average number of people waiting to open accounts? (Points :
2)
3.27
4.16
5.27
5.83
Question
7. 7.A suburban specialty restaurant has developed a single
drive-thru window. Customers order, pay, and pick up their food at the
same window. Arrivals follow a Poisson distribution while service times
follow an exponential distribution. If the average number of arrivals is
6 per hour and the service rate is 2 every 15 minutes, how much time will
elapse (in hours) from the time a customer enters the line until he/she
leaves the restaurant? (Points : 2)
0.50
0.25
0.75
2.25
3.00
Question
8. 8.A widely used mathematical programming technique designed to
help managers and decision making relative to resource allocation is
called __________. (Points : 2)
linear programming
computer programming
constraint programming
goal programming
None of the above
Question
9. 9.Consider the following linear programming problem:
Maximize 12X + 10Y
Subject to:
4X + 3Y ? 480
2X + 3Y ? 360
all variables ? 0
The maximum possible value for the objective function is __________.
(Points : 2)
360
480
1,520
1,560
none of the above
Question
10. 10.If items being transported must go through an intermediate
point before reaching a final destination, then this situation is known
as a(n) __________. (Points : 2)
transshipment problem
assignment problem
transportation problem
intermediate point problem
None of the above
Question
11. 11.Which of the following is not a popular definition
of quality? (Points : 2)
Quality is the totality of features and characteristics of a product or
service that bears on its ability to satisfy stated or implied needs.
Quality is defined as
a competitively priced product that surpasses customer needs.
Quality is the degree to which a product conforms to design or
specification.
Quality is fitness for use.
Even though quality cannot be defined, you know what it is.
Question
12. 12.Variations that usually occur in a process are called
__________. (Points : 2)
process variations
natural variations
control variations
assignable variations
none of the above
Question
13. 13.A feasible solution to a linear programming problem:
(Points : 2)
must be a corner point of the feasible region.
must satisfy all of
the problem's constraints simultaneously.
need not satisfy all of the constraints, only the non-negativity
constraints.
must give the maximum possible profit.
must give the minimum possible cost.
Question
14. 14.Click here to view
a Word version of the table.
To guarantee that cans of soup are properly filled, some cans are sampled
and the amounts measured. The overall average for the samples is 12
ounces. Each sample contains 10 cans. The average range is 0.4 ounces.
Using the data in the table above, what is the lower control chart limit
for the sample averages? (Points : 2)
12.1232
11.8768
13.2
12.308
None of the above
Question
15. 15.Which of the following control charts is/are for
attributes? (Points : 2)
p-chart x-bar chart R-chart
A and B
A, B, and C
Question
16. 16.A certain firm has four different operations that must be
assigned to four locations. The profit (in thousands of dollars)
associated with each operation at each location is presented below. The
firm's vice president would like to assign the various operations so that
the total profit is maximized. Find the appropriate assignments.
Click here to view
an Excel version of the table.
Using the data in the table, what is the optimal location for Operation
Z? (Points : 2)
1
2
3
4
Question
17. 17.Given the table below, the final table for an assignment
problem, who should be assigned to Job 2?
Click here to view
an Excel version of the table.
(Points : 2)
Worker A
Worker C
Either worker A or worker C
Neither worker A nor worker C
Worker D
Question
18. 18.A company believes a process monitored by an x-bar
chart to be in control. When the most recent control point exceeded the
UCL value by 20%, the company should: (Points : 2)
believe that a random bad luck chance occurred and proceed.
suspect that an
assignable cause of variation now exists and can be found.
ignore the control point completely, as it is simply an outlier.
wait for the next four samples to be taken to see if a trend develops.
none of the above.
Question
19. 19.Click here to view
a Word version of the table.
Bags of chocolate candy are sampled to ensure proper weight. The overall
average for the samples is 36 ounces. Each sample contains twelve bags.
The average range is 1.3 ounces.
Using the data in the table above, what is the lower control chart limit
for the sample averages? (Points : 2)
36.3730
36.4849
35.6270
35.5150
Question
20. 20.Consider the following linear programming model:
a unique optimal solution.
an unbounded solution.
an infeasible solution.
an alternate optimal solution.
redundant constraints.
Question
21. 21.When using the shortest-route technique, the second step
is to: (Points : 2)
find the next-nearest
node to the origin and put the distance in a box by the node.
trace the path from the warehouse to the plant.
determine the average distance traveled from source to end.
find the nearest node to the origin and put a distance box by the node.
None of the above is correct.
Question
22. 22.The shortest-route technique would best be used to:
(Points : 2)
assign workers to jobs in the cheapest manner.
determine the number of units to ship from each source to each destination.
determine the amount of LAN network wiring within a building.
minimize the amount of traffic flow on a busy highway.
determine the path for
a truck making frequent but repeatable drops.
Question
23. 23.The p-chart is useful when we: (Points : 2)
take a number of measurements and compute the average.
take a number of measurements and compute the ranges.
find the fraction of
the production lot defective.
find the number of defective items in a production lot.
None of the above is correct.
Question
24. 24.A finite population model differs from an infinite
population model because there is a random relationship between the
length of the queue and the arrival rate. (Points : 2)
True
False
Question
25. 25.The wait time for a single-channel system is more than
twice that for a two-channel system using two servers working at the same
rate as the single server. (Points : 2)
True
False
Question
26. 26.The maximal-flow technique finds the maximum flow of any
quantity or substance through a network. (Points : 2)
True
False
Question
27. 27.Two characteristics of arrivals are the line length and
queue discipline. (Points : 2)
True
False
Question
28. 28.The points on the network are referred to as nodes. (Points
: 2)
True
False
Question
29. 29.In the maximal-flow technique, a zero (0) means no flow or
a one-way arc. (Points : 2)
True
False
Question
30. 30.Infeasibility in a linear programming problem occurs when:
(Points : 2)
there is an infinite solution.
a constraint is redundant.
more than one solution is optimal.
the feasible region is unbounded.
there is no solution
that satisfies all the constraints given.
Question
31. 31.A certain firm has four different operations that must be
assigned to four locations. The profit (in thousands of dollars)
associated with each operation at each location is presented below. The
firm's vice president would like to assign the various operations so that
the total profit is maximized. Find the appropriate assignments.
Click here to view
an Excel version of the table.
Using the data in the table, what is the optimal location for Operation
W? (Points : 2)
1
2
3
4
Question
32. 32.In a single-channel, single-phase system, reducing the
service time only reduces the total amount of time spent in the system,
not the time spent in the queue. (Points : 2)
True
False
Question
33. 33.A company can decide how many additional labor hours to
acquire for a given week. Subcontractor workers will only work a maximum
of 20 hours a week. The company must produce at least 200 units of
product A, 300 units of product B, and 400 units of product C. In 1 hour
of work, worker 1 can produce 15 units of product A, 10 units of product
B, and 30 units of product C. Worker 2 can produce 5 units of product A,
20 units of product B, and 35 units of product C. Worker 3 can produce 20
units of product A, 15 units of product B, and 25 units of product C.
Worker 1 demands a salary of $50/hr, worker 2 demands a salary of $40/hr,
and worker 3 demands a salary of $45/hr. The company must choose how many
hours they should contract with each worker to meet their production
requirements and minimize labor cost.
Assuming this is a linear programming problem, which of the following is
the optimal solution? (Points : 2)
Question
34. 34.A company must assign mechanics to each of four jobs.
Click here to view
an Excel version of the table.
The time involved varies according to individual abilities. The table
shows how many minutes it takes each mechanic to perform each job. If the
optimal assignments are made, how many total minutes would be required
for completing the jobs? (Points : 2)
0
4
17
16
None of the above
Question
35. 35.The customer who arrives at a bank, sees a long line, and
leaves to return another time is __________. (Points : 2)
balking
cropping
reneging
blithering
none of the above.
Question
36. 36.Two models of a product — Regular (X) and Deluxe (Y) — are
produced by a company. A linear programming model is used to determine
the production schedule. The formulation is as follows:
Maximize profit = 50X + 60Y
Subject to:
8X + 10Y ? 800 (labor hours)
X + Y ?
120
(total units demanded)
4X = 5Y ? 500 (raw
materials)
all variables ? 0
The optimal solution is X = 100, Y = 0.
How many units of the regular model would be produced based on this
solution? (Points : 2)
0
100
50
120
None of the above
Question
37. 37.In PERT, we assume that: (Points : 2)
the times to complete individual activities are known with certainty.
all activities are carried out by staff from our own organization.
the total cost of a project is independent of the time to complete the
project.
the total time to
complete all activities on the critical path is described by a normal
distribution.
none of the above.
Question
38. 38.The difference between the left-hand side and right-hand
side of a greater-than-or-equal-to constraint is referred to as
__________. (Points : 2)
surplus
constraint
slack
shadow price
none of the above
Question
39. 39.A suburban specialty restaurant has developed a single
drive-thru window. Customers order, pay, and pick up their food at the
same window. Arrivals follow a Poisson distribution while service times
follow an exponential distribution. If the average number of arrivals is
6 per hour and the service rate is 2 every 15 minutes, what proportion of
the time is the server busy? (Points : 2)
0.25
0.50
0.75
2.25
3.00
Question
40. 40.Which of the following is not an assumption of LP?
(Points : 2)
are infeasible
are unbounded
are degenerate
are unbalanced
provide management
with greater flexibility in selecting and using resources
Question
42. 42.Cars arrive at a local JLUBE franchise at the rate of 1
every 12 minutes. Service times are exponentially distributed with an
average of 15 minutes. Jack Burns, the JLUBE owner, has decided to open a
second work bay, i.e., make the shop into a two-channel system. Under
this new scheme, the total time an average customer spends in the system
will be (Points : 2)
Question
43. 43.An automatic car wash is an example of a constant service
time model. (Points : 2)
True
False
Question
44. 44.Customers enter the waiting line to pay for food as they
leave a cafeteria on a first-come, first-served basis. The arrival rate
follows a Poisson distribution, while service times follow an exponential
distribution. If the average number of arrivals is four per minute and
the average service rate of a single server is seven per minute, on
average, how much time will elapse from the time a customer enters the
line until he/she leaves the cafeteria? (Points : 2)
Question
45. 45.A certain firm has four different operations that must be
assigned to four locations. The profit (in thousands of dollars)
associated with each operation at each location is presented below. The
firm's vice president would like to assign the various operations so that
the total profit is maximized. Find the appropriate assignments.
Click here to view
an Excel version of the table.
Using the data in the table, what is the optimal location for Operation
X? (Points : 2)
1
2
3
4
Question
46. 46.Which of the following is not a property of all
linear programming problems? (Points : 2)
The presence of restrictions
Optimization of some objective
A computer program
Alternate courses of action to choose from
Usage of only linear equations and inequalities
Question
47. 47.Typical resources of an organization include __________.
(Points : 2)
machinery usage
labor volume
warehouse space utilization
raw material usage
all of the above
Question
48. 48.Assume that we are using a waiting line model to analyze
the number of service technicians required to maintain machines in a
factory. Our goal should be to: (Points : 2)
maximize productivity of the technicians.
minimize the number of machines needing repair.
minimize the downtime for individual machines.
minimize the percent of idle time of the technicians.
minimize the total
cost (cost of maintenance plus cost of downtime).
Question
49. 49.The shortest-route technique might be logically used for:
(Points : 2)
finding the longest time to travel between two points.
finding the shortest
travel distance between two points.
finding the most scenic route to allow travel to several places during a
trip on spring break.
connecting all the points of a network together while minimizing the
distance between them.
none of the above.
Question
50. 50.The c-chart is useful when we: (Points : 2)
take a number of measurements and compute the average.
take a number of measurements and compute the ranges.
find the fraction of the production lot defective.
find the number of
defective items in a production lot.
None of the above is correct
Solution: Saint GBA334 final exam-100% correct