Question 1 of 20 5.0 Points What is a milestone?

Question # 00003193 Posted By: expert-mustang Updated on: 11/05/2013 11:02 PM Due on: 11/06/2013
Subject Economics Topic General Economics Tutorials:
Question
Dot Image

Question 1 of 20 5.0 Points

What is a milestone?
A. A significant event in the project

B. A mark on a chart that depicts project progress

C. An activity on the critical path

D. An activity with an uncertain completion time
Reset Selection

Mark for Review What's This?
Question 2 of 20 5.0 Points

What is project slack?
A. The amount of time a non-critical task can be delayed without making the project late

B. The amount of time the critical path of a project can be delayed without making the project late

C. The amount of time an activity on the critical path can be delayed without making the project late

D. The difference between how long the project would take if all tasks were completed based on their pessimistic versus optimistic time estimates
Reset Selection

Mark for Review What's This?
Question 3 of 20 5.0 Points

For which purpose is simulation NOT used with regard to project scheduling?
A. To overcome the limitations associated with statistical techniques used to develop probability of completion time estimates

B. To investigate the range of project completion times

C. To investigate the distribution of project completion times

D. To verify the accuracy of the optimistic, pessimistic, and most likely time estimates

Question 4 of 20 5.0 Points

Technical dependencies on a project plan are easiest to see on a:
A. Gantt chart.

B. GERT chart.

C. PERT/CPM chart.

D. Work Breakdown Structure.

Question 5 of 20 5.0 Points

PERT was originally used for what type of project?
A. Construction

B. R & D

C. Military

D. Computer software development

Question 6 of 20 5.0 Points

Which of the following is NOT an element of the Gantt chart?
A. Actual progress

B. Variance of the critical path

C. The current date

D. Scheduled milestones

Question 7 of 20 5.0 Points

Which of the following is typically used as the best estimate of task duration?
A. Expected time

B. Pessimistic time

C. Optimistic time

D. Most likely time

Question 8 of 20 5.0 Points

Which of the following terms is most closely associated with a task required by the project?
A. Activity

B. Event

C. Milestone

D. Network

Question 9 of 20 5.0 Points

What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively?
A. 3

B. 4

C. 4.3

D. 4.7

Question 10 of 20 5.0 Points

What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days, respectively, assuming the estimates were made at the 99% plus level?
A. .444

B. .667

C. 1.212

D. 1.469

Question 11 of 20 5.0 Points

The amount of time a noncritical task can be delayed without delaying the project is called:
A. surplus.

B. flop.

C. slack.

D. critical time.

Question 12 of 20 5.0 Points

Slack is calculated as:
A. LFT – EST.

B. LFT – LST.

C. LST – LFT.

D. LFT – EFT.

Question 13 of 20 5.0 Points

Which of the following linkages is used to start two or more activities at the same time?
A. Finish-to-start

B. Start-to-start

C. Finish-to-finish

D. Start-to-finish


Question 14 of 20 5.0 Points

One shortcoming of the __________ network method is that it does not allow for leads and lags between two activities without greatly increasing the number of subactivities to account for this.
A. Gantt Chart

B. AON

C. MSP

D. PERT/CPM

Question 15 of 20 5.0 Points

An identifiable state resulting from the completion of one or more activities is called:
A. an event.

B. an activity.

C. a milestone.

D. a path.
Reset Selection


Question 16 of 20 5.0 Points

The major advantage of the Gantt chart is that it:
A. addresses all activities.

B. is easy to read.

C. highlights critical task of the project.

D. manages project scheduling.
Reset Selection


Question 17 of 20 5.0 Points

A(n) __________ is an identifiable state resulting from the completion of one or more activities.
A. path

B. milestone

C. critical path

D. event
Reset Selection

Question 18 of 20 5.0 Points
For any task on a critical path, its __________ must be the same as its __________.

A. LST; LFT


B. LFT; EFT


C. LST; EST


D. EST; EFT
Reset Selection

Mark for Review What's This?

Question 19 of 20 5.0 Points
The amount of time a noncritical task can be delayed without delaying the project is called:

A. margin.


B. completion variance.


C. float.


D. variable duration.
Reset Selection

Mark for Review What's This?

Question 20 of 20 5.0 Points
The square root of the variance of statistical distribution equals the __________ of that distribution.

A. standard deviation


B. normal probability


C. variance of the path


D. cumulative probability
Reset Selection


Dot Image
Tutorials for this Question
  1. Tutorial # 00002978 Posted By: expert-mustang Posted on: 11/05/2013 11:04 PM
    Puchased By: 5
    Tutorial Preview
    to complete a task with optimistic, most likely, and pessimistic ...
    Attachments
    Solution-00002978.zip (113 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    cu...iki Rating Top-quality and well-detailed work 05/21/2015
    jm...79 Rating Make learning interesting 10/23/2014
    hap...111 Rating Multiple payment options 09/29/2014

Great! We have found the solution of this question!

Whatsapp Lisa