Liberty BUSI681 2020 April Quiz 8 Latest
BUSI681 Advanced Project Management 2
Quiz 8
Question 1Plan driven methods of Project Management will suffer when the project Scope and Technology are not fully known.
Question 2Securing the cooperation of customers to devote the necessary time to support agile project management is a common source of frustration in the field.
Question 3In many cases, _________ only begin to understand what they actually desire when they are provided with someone's impression of what they want.
Question 4Iterations are short time frames (time boxes) that typically last from ___________.
Question 5Traditional approaches to project management concentrate firmly on
Question 6Project ________ varies according to the extent the project scope is known and stable and the technology to be used is known and proven.
Question 7Scrum does not use any of the conventional project management tools like Gantt charts or network diagrams.
Question 8When determining project uncertainty, _________ can be a source of unpredictability.
Question 9For some agile projects, ___________ are established, which is the maximum budget that should not be exceeded in the development of a given product or service.
Question 10When the project scope and/or technology are not fully known, things become much less predictable.
Question 11Owners have the option to change features and priorities at the end of each sprint if desired. However, no changes should be made once a sprint has started.
Question 12The third phase of the Scrum development process is to build the feature so that it is functional.
Question 13A new holistic approach in new commercial product development efforts where the cross-functional team collaborating to develop a new product is compared to rugby, where the whole team tries to go the distance as a unit is known as
Question 14A disadvantage of an iterative development process used in agile project management is that it is difficult to detect defects and problems early.
Question 15While agile project management does not consist of one set method, most methods are based on similar principles. Which of the following agile project management principles would be described when employing business-driven prioritizations of requirements and features to satisfy customer needs?
Question 16The goal of each sprint is to produce fully functional features.
Question 17Scrum relies on three key roles. A person who acts on behalf of customers to represent their interests and who is responsible for ensuring that the development team focuses their efforts on developing a project that will fulfill the business objective of the project is called a
Question 18Iterative development processes provide the following important advantages EXCEPT
Question 19The Scrum master is not the leader of the team but acts as a buffer between the team and outside interferences.
Question 20The product owner has the option to change features and priorities at the end of each sprint if desired.
Question 21Freezing the design as late as possible is a common characteristic of the agile project management model.
Question 22Specific features are created using Scrum methodology according to four distinct phases. Which of the following is NOT one of these phases?
Question 23Specific features are created using Scrum methodology according to four distinct phases. Which of the following places these phases in the correct order?
Question 24Agile methods appear to work best on small projects that require only five to nine dedicated team members to complete the work.
Question 25Each new iteration replaces the work of the previous iterations and adds new capabilities to the evolving to produce a next expanded version of the product.
Question 26In order to hedge against unpredictability within a project, Agile Project Management uses
Question 27The _________ is the customer's prioritized list of key features desired when the project is completed.
Question 28_______________ is the Agile principle in which the team creates a flow of value to the stakeholder(s) or customer(s) by delivering smaller, functional increments of the project.
Question 29Traditional project management practices require
Question 30Which of the following is NOT true of a development team using Scrum methodology?
-