Calculate the project completion time.

Question # 00030420 Posted By: maqj Updated on: 11/03/2014 08:43 AM Due on: 11/30/2014
Subject Business Topic Management Tutorials:
Question
Dot Image

Question 1

Table 1

Complete the following:

1. Calculate the project completion time.

2. Indicate the critical path activities.

3. What is the probability of completing this project between 38 and 40 days?

4. What are the slack values for activities C and F? Interpret the meaning of their slack values?

Question 2

A registered nurse is trying to develop a diet plan for patients. The required nutritional elements are the total daily requirements of each nutritional element as indicated in Table 2:

Required nutritional element total and daily requirements

Table 2

The nurse has four basic types to use when planning the menus. The units of nutritional element per unit of food type are shown in Table 3 below. Note that the cost associated with a unit of ingredient also appears at the bottom of Table 3.

Required nutritional element and units of nutritional elements per unit of food type

Table 3

Moreover, due to dietary restrictions, the following aspects should also be considered when developing the diet plan:

1. The chicken food type should contribute at most 25% of the total caloric intake that will result from the diet plan.

2. The vegetable food type should provide at least 30% of the minimum daily requirements for vitamins.

Complete the following:

Provide a linear programming formulation for the above case.

Dot Image
Tutorials for this Question
  1. Tutorial # 00029866 Posted By: maqj Posted on: 11/03/2014 08:45 AM
    Puchased By: 4
    Tutorial Preview
    The solution of Calculate the project completion time....
    Attachments
    Sol_138.xlsx (34.59 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    swah...il.com Rating Great quality and professional work 03/18/2015
    bu...rkp Rating Instant and best chat service 12/26/2014

Great! We have found the solution of this question!

Whatsapp Lisa