a project consists of 5 activities. the paint mixing
Question # 00401322
Posted By:
Updated on: 10/08/2016 01:14 AM Due on: 10/08/2016

a project consists of 5 activities. the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. Develop a complete network. what is the estimated completion time of the project? identify the critical path of the project. what is the profitability the project will be completed in 9 hours (assume the variance=6 hours)
floor sanding optimistic (3) Most probable(4) pessimistic(5)
floor buffing optimistic(1) Most probable(2) pessimistic(3)
paint mixing (0.5) (1) (1.5)
wall painting (1) (2) (9)
ceiling painting (1) (5.5) (7)

-