a project consists of 5 activities. the paint mixing

Question # 00401322 Posted By: rey_writer Updated on: 10/08/2016 01:14 AM Due on: 10/08/2016
Subject Statistics Topic General Statistics Tutorials:
Question
Dot Image

a project consists of 5 activities. the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. Develop a complete network. what is the estimated completion time of the project? identify the critical path of the project. what is the profitability the project will be completed in 9 hours (assume the variance=6 hours)


floor sanding optimistic (3) Most probable(4) pessimistic(5)

floor buffing optimistic(1) Most probable(2) pessimistic(3)

paint mixing (0.5) (1) (1.5)

wall painting (1) (2) (9)

ceiling painting (1) (5.5) (7)

Dot Image
Tutorials for this Question
  1. Tutorial # 00396554 Posted By: rey_writer Posted on: 10/08/2016 01:14 AM
    Puchased By: 3
    Tutorial Preview
    The solution of a project consists of 5 activities. the paint mixing...
    Attachments
    To_do_this_problem_first_we_need_to_calculate_deterministic_time_for_all_the_activities.docx (5159.26 KB)