You are creating a customer database for the Modesto Nuts minor league

Question # 00247074 Posted By: solutionshere Updated on: 04/10/2016 04:24 PM Due on: 05/10/2016
Subject Accounting Topic Accounting Tutorials:
Question
Dot Image

You are creating a customer database for the Modesto Nuts minor league
baseball team. Draw a project network given the information below. Complete
the forward and backward pass, compute activity slack, and identify the
critical path.
How long will this project take? How sensitive is the network schedule?
Calculate the free slack and total slack for all noncritical activities.

Provide the Early Start, Early Finish, Late Start, and Late Finish times for each activity. Compute the Total Slack for each activity. Determine which activities are on the critical path. How long will it take to complete the project?

An activity that is on the critical path for this project has increased by 7. Will the project end date be delayed? If so, by how much?

ID Description Predecessor (days)
A Systems design None 2
B Subsystem A design A 1
C Subsystem B design A 1
D Subsystem C design A 1
E Program A B 2
F Program B C 2
G Program C D 2
H Subsystem A test E 1
I Subsystem B test F 1
J Subsystem C test G 1
K Integration H, I, J 2
L Integration test K 1

Dot Image
Tutorials for this Question
  1. Tutorial # 00242312 Posted By: solutionshere Posted on: 04/10/2016 04:24 PM
    Puchased By: 3
    Tutorial Preview
    baseball team. Draw a project ...
    Attachments
    Modesto_Nuts.docx (35.05 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    T...rl! Rating On-time delivery of the tutorials 02/20/2019

Great! We have found the solution of this question!

Whatsapp Lisa