Week 8 Individual Project and assignment

Question 1
Frank’s machine shop operates 250 days per year. Frank sells 5,000 units per year of his most popular item, a specialty gear. The set-up cost for this gear is £100 and the monthly unit cost of holding inventory is 1% of the production cost per unit, which is £50. The lead time is 10 days. When the gear is being produced, the shop can make 80 gears per day (Hint: You should use the production model for inventory management.).
Complete the following:
1. How many gears should be produced in each run and at what minimum cost?
2. What is the cycle time?
3. Find the reorder point.
4. Draw a graph to depict inventory level against time and show on it the quantities found above. Also, what is the maximum inventory level?
Question 2
Complete the five discussion questions in the case study on page 444 (Dell’s Value Chain) in the Heizer and Render (2011) textbook.
Week 8
Individual Project
The purpose of this simulation project is to provide you with an opportunity to use the POM-QM for Windows software to solve an MRP problem.
POM-QM for Windows software
For this part of the Individual Project, you need to use the POM-QM for Windows software:
- Read Appendix IV of the Operations Management (Heizer & Render, 2011) textbook.
- Launch the POM-QM for Windows software and from the main menu select Module, and then Materials Resource Planning.
- Program the MRP for the Individual Project Problem below and solve it with the use of POM-QM for Windows. (Refer to Appendix IV in the Heizer and Render (2011) textbook.)
Individual Project Problem
The product structure tree for the finished product A is given below.
The marketing department is estimating product A’s demand to be 60 units for week 4 and 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products and the components are provided below.
|
A |
C |
D |
E |
On hand |
12 |
170 |
9 |
5 |
Lead time |
2 |
2 |
1 |
1 |
Lot size |
LFL |
150+ |
multiples of 40 |
multiples of 22 |
Provide the MRP tables for all the finished products and the components for the next six weeks.

-
Rating:
5/
Solution: Week 8 Individual Project and assignment