week 7 quiz 1- Compare and contrast top-down and bottom-up project estimating techniques

1. Compare and contrast top-down and bottom-up project estimating techniques
2.
You
are comparing two projects. Using the data below, calculate the CV, SV, SPI,
and CPI. Second, use the values to provide the status of each
project. All values are in dollars.
|
Project A |
Project B |
EV |
450 |
550 |
PV |
465 |
575 |
AC |
425 |
650 |
3. Describe the 4-step general model of project control. Provide examples of each step.
4. All projects suffer from some form of conflict at one time or another. List and describe four common sources of conflict on a project and provide examples of each from either a recent project or from your personal life.
5. Compare and contrast project control in an agile environment and in a traditional environment.

-