The estimated times and immediate predecessors for the activities in a project at John Black’s company
Question # 00073000
Posted By:
Updated on: 05/27/2015 03:04 AM Due on: 05/27/2015

The estimated times and immediate predecessors for the activities in a project at John Black’s company are given in the following table. Assume that the activity times are independent. All times are in weeks.
Activity | Predecessors | Optimistic Time (a) | Most Likely Time (m) | Pessimistic Time (b) |
A | -- | 2 | 4 | 6 |
B | -- | 1 | 2 | 9 |
C | A | 2 | 4 | 6 |
D | B | 5 | 8 | 17 |
E | C | 3 | 4 | 11 |
What is the critical path? You may use any method to determine this.
What is the expected completion time of the project?
What is the probability of completing the project in 16 weeks or more?

-
Rating:
5/
Solution: The estimated times and immediate predecessors for the activities in a project at John Black’s company