The estimated times and immediate predecessors for the activities in a project at John Black’s company

Question # 00073000 Posted By: solutionshere Updated on: 05/27/2015 03:04 AM Due on: 05/27/2015
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

The estimated times and immediate predecessors for the activities in a project at John Black’s company are given in the following table. Assume that the activity times are independent. All times are in weeks.

Activity

Predecessors

Optimistic Time (a)

Most Likely Time (m)

Pessimistic Time (b)

A

--

2

4

6

B

--

1

2

9

C

A

2

4

6

D

B

5

8

17

E

C

3

4

11

  1. What is the critical path? You may use any method to determine this.

  2. What is the expected completion time of the project?

  1. What is the probability of completing the project in 16 weeks or more?


Dot Image
Tutorials for this Question
  1. Tutorial # 00067636 Posted By: solutionshere Posted on: 05/27/2015 03:05 AM
    Puchased By: 5
    Tutorial Preview
    = 12 weeks So, Critical path is ...
    Attachments
    2260011.docx (48.34 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    spry...o.com Rating The homework was precisely done 04/07/2016
    R...27 Rating Provide the work at reasonable prices 06/29/2015
    thi...ng1 Rating Amazed with their instant service support 06/29/2015

Great! We have found the solution of this question!

Whatsapp Lisa