(TCO B) You are a project manager at a bike shop

Question # 00362793 Posted By: SVExpert Updated on: 08/14/2016 07:43 AM Due on: 08/14/2016
Subject General Questions Topic College life Tutorials:
Question
Dot Image
(TCO B) You are a project manager at a bike shop. You just received a shipment of new bikes that need to be assembled. The frames need to be set, which includes the bike frame, handlebars, and seat. The wheels need to be mounted. The braking system needs to be installed. Before the bike can be sold, it needs to be tested by the quality team and road tested. You have assembled your team of experts, and they are anxious to get started.







a) To ensure you have a clear scope for your team, create a two-level WBS. Don’t forget to include your WBS numbering. (20 points)



b) In your WBS, how many work packages have been created? (10 points) (Points : 25)
Dot Image
Tutorials for this Question
  1. Tutorial # 00358475 Posted By: SVExpert Posted on: 08/14/2016 07:44 AM
    Puchased By: 3
    Tutorial Preview
    The solution of (TCO B) You are a project manager at a bike shop...
    Attachments
    Set_bike_frame.docx (11.99 KB)

Great! We have found the solution of this question!

Whatsapp Lisa