Saint GBA334 module 7 quiz

Question # 00036009 Posted By: shortone Updated on: 12/12/2014 06:43 AM Due on: 12/31/2014
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image
Question 1.1.

In a PERT network, the earliest (activity) start time is the

(Points : 4)






Question 2.2.

PERT and CPM are quantitative analysis tools designed to schedule and control large projects.

(Points : 4)



Question 3.3.

The expected time in PERT is

(Points : 4)






Question 4.4.

On a practical note — if we are using waiting line analysis to study customers calling a telephone number for service, balking is probably not an issue.

(Points : 4)



Question 5.5.

An arrival in a queue that reneges is one who

(Points : 4)






Question 6.6.

PERT was developed for a project for which activity or task times were uncertain.

(Points : 4)



Question 7.7.

The following represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

A

-

2

8

14

B

-

8

8

8

C

A

6

9

18

D

B

5

11

17

According to the data in Table above, what is the minimum expected completion time for the project?


(Points : 4)






Question 8.8.

A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution while service times follow an exponential distribution. If the average number of arrivals is 6 per hour and the service rate is 2 every 15 minutes, what is the average number of customers waiting in line behind the person being served?

(Points : 4)






Question 9.9.

Given the following small project, the critical path is ________ days.

Activity

Immediate

Predecessor

Time

(days)

A

-

10

B

-

4

C

A, B

6

(Points : 4)






Question 10.10.

The study of waiting lines is called queuing theory.

(Points : 4)



Question 11.11.

Slack is the time an activity can be delayed without impacting the completion time of the project.

(Points : 4)



Question 12.12.

CPM was developed for use in managing projects about which we have good information about activity or task completion times.

(Points : 4)



Question 13.13.

In queuing analysis, total expected cost is the sum of expected ________ plus expected ________.

(Points : 4)






Question 14.14.

One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail—and thus come to an understanding of relationships between the activities.

(Points : 4)



Question 15.15.

Given the following small project, the critical path is ________ days.

Activity

Immediate

Predecessor

Time

(days)

A

-

8

B

A

4

C

-

10

(Points : 4)






Question 16.16.

A bank with a single queue to move customers to several tellers is an example of a single-channel system.

(Points : 4)



Question 17.17.

Slack time in a network is the

(Points : 4)






Question 18.18.PERT is a deterministic analysis tool allowing for precise times of activities within a project.(Points : 4)



Question 19.19.

Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.

(Points : 4)






Question 20.20.

Frequently in queuing problems, the number of arrivals per unit of time can be estimated by a probability distribution known as the Poisson distribution.

(Points : 4)



Question 21.21.

The customer who arrives at a bank, sees a long line, and leaves to return another time is

(Points : 4)






Question 22.22.

A goal of many waiting line problems is to help a firm find the ideal level of services that minimize the cost of waiting and the cost of providing the service.

(Points : 4)



Question 23.23.

Lines at banks where customers wait for a teller window are usually representative of a

(Points : 4)






Question 24.24.

One difficulty in waiting line analysis is that it is sometimes difficult to place a value on customer waiting time.

(Points : 4)



Question 25.25.

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.

(Points : 4)






Dot Image
Tutorials for this Question
  1. Tutorial # 00035299 Posted By: shortone Posted on: 12/12/2014 06:57 AM
    Puchased By: 3
    Tutorial Preview
    The solution of Saint GBA334 module 7 quiz-100% correct...
    Attachments
    Saint_GBA334_module_7_quiz.docx (124.8 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    le...n50 Rating Highly satisfactory results 05/23/2015

Great! We have found the solution of this question!

Whatsapp Lisa