Question 1.1.Which of the following statements about project crashing is false?(Points : 3)






Question 2.2.Considering the following Activity-On-Node (AON) project (activity completion times are in days),what is the critical path?

Activity-On-Node

Click hereto view a Word version of the project.
(Points : 3)





Question 3.3.Considering the following Activity-On-Node (AON) project (activity completion times are in days),what is the slack time associated with activity E?

Activity-On-Node

Click hereto view a Word version of the project.
(Points : 3)





Question 4.4.Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively.What is the standard deviation associated with the completion time of activity B?

Activity-On-Node-2

Click hereto view a Word version of the project.
(Points : 3)





Question 5.5.Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively.What is the expected completion time of the critical path?

Activity-On-Node-2

Click hereto view a Word version of the project.
(Points : 3)





Question 6.6.Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B A
C A
D B, C
E B, C
F D, E
G F

Jamie was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 4
B 4
C 5
D 3
E 3
F 2
G 1

Considering the information above, what is the slack for activities E and F respectively?
(Points : 3)





Question 7.7.Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate
Activity
Predecessors
A -
B -
C A, B
D C
E C
F D, E
G E
H F, G


Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2

Considering the information above, what is the earliest finish time for activity F?
(Points : 3)





Question 8.8.Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate
Activity
Predecessors
A -
B -
C A, B
D C
E C
F D, E
G E
H F, G


Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2

Considering the information above, what is the critical path?
(Points : 3)





Question 9.9.Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5

Considering the information above, what is the length of the project?
(Points : 3)





Question 10.10.Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate
Activity
Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5

Considering the information above, what is the critical path?
(Points : 3)





Dot Image
Tutorials for this Question
  1. Tutorial # 00055481 Posted By: shortone Posted on: 04/05/2015 07:11 PM
    Puchased By: 7
    Tutorial Preview
    The solution of Saint GBA334 module 5 quiz 3...
    Attachments
    Saint_GBA334_module_5_quiz_3.docx (124.66 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    g...nh Rating Brilliant tutorials 08/31/2016
    K...J Rating Provide assignments on time 08/31/2016
    lu...nyc Rating Great services and offers 10/27/2015
    mr...unk Rating Professional and helpful tutors 09/02/2015
    be...0731 Rating Helped in securing A+ grade 07/07/2015

Great! We have found the solution of this question!

Whatsapp Lisa