SAINT GBA334 MODULE 5 QUIZ 3

Question # 00051828 Posted By: spqr Updated on: 03/03/2015 10:01 AM Due on: 03/21/2015
Subject Business Topic General Business Tutorials:
Question
Dot Image

Which of the following statements about project crashing is false?

The overall project time is reduced by crashing activities on one or more critical paths.

It is best to crash an activity with the cheapest cost to crash per week.

As activities are crashed in a project network, it is possible for more than one path to be critical.

In order to reduce the overall project time, it may be necessary to crash more than one activity.

Project crashing problems can be solved using linear programming.

Points Received: 0 of 3

Question 2. Question :

Considering the following Activity-On-Node (AON) project (activity completion times are in days), what is the slack time associated with activity D?

Activity-On-Node

Click here to view a Word version of the project.

0 days

1 day

2 days

3 days

Question 3. Question :

Considering the following Activity-On-Node (AON) project (activity completion times are in days), how long will it take to complete the project?

Activity-On-Node

Click here to view a Word version of the project.

13 days

14 days

15 days

16 days

Question 4. Question :

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the expected completion time of the critical path?

Activity-On-Node-2

Click here to view a Word version of the project.

14 days

19 days

20 days

23 days

Question 5. Question :

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the probability of completing the project within 18 days?

Activity-On-Node-2

Click here to view a Word version of the project.

0.0612

0.0668

0.0733

0.0795

Question 6. Question :

Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B A

C A

D B, C

E B, C

F D, E

G F

Jamie was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 4

B 4

C 5

D 3

E 3

F 2

G 1

Considering the information above, what is the earliest finish time for activity F?

10 days

11 days

13 days

14 days

Question 7. Question :

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors

A -

B -

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the length of the project?

10 days

12 days

14 days

16 days

Question 8. Question :

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors

A -

B -

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the earliest finish time for activity F?

10 days

12 days

14 days

16 days

Question 9. Question :

Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B -

C -

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the earliest finish time for activity E?

5 days

6 days

7 days

8 days

Question 10. Question :

Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B -

C -

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the critical path?

CEGHJ

ADFIJ

CEFIJ

ADFHJ

Dot Image
Tutorials for this Question
  1. Tutorial # 00048989 Posted By: spqr Posted on: 03/03/2015 10:03 AM
    Puchased By: 14
    Tutorial Preview
    The solution of SAINT GBA334 MODULE 5 QUIZ 3...
    Attachments
    SAINT_GBA334_MODULE_5_QUIZ_3._._._.docx (68.53 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    ama...rsey Rating Highly informative tutorials 05/09/2017
    rob...l28 Rating Customised services and great experience 12/19/2016
    f...ech Rating Quite presentable tutorials 12/17/2016
    th...er Rating The presentation of work is very effective 10/20/2016
    K...J Rating Instant customer support services 08/31/2016

Great! We have found the solution of this question!

Whatsapp Lisa