Question 1. Question :

A graph that plots the total resources needed per period vs. time is called a(n) __________.

: Gantt Chart

Resource Loading Chart

Work Breakdown Structure

Project Network Chart

PERT/CPM Chart

Question 2. Question :

Considering the following Activity-On-Node (AON) project (activity completion times are in days), what is the slack time associated with activity E?

Activity-On-Node

Click here to view a Word version of the project.

0 days

1 day

2 days

3 days

3 of 3

Question 3. Question :

Considering the following Activity-On-Node (AON) project (activity completion times are in days), how long will it take to complete the project?

Activity-On-Node

Click here to view a Word version of the project.

13 days

14 days

15 days

16 days

3 of 3

Question 4. Question :

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the standard deviation associated with the completion time of activity B?

Activity-On-Node-2

Click here to view a Word version of the project.

0.0245 days

0.6667 days

0.3145 days

0.3333 days

3 of 3

Question 5. Question :

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the expected completion time of activity A?

Activity-On-Node-2

Click here to view a Word version of the project.

2 days

3 days

4 days

5 days

3 of 3

Question 6. Question :

Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B A

C A

D B, C

E B, C

F D, E

G F

Jamie was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 4

B 4

C 5

D 3

E 3

F 2

G 1

Considering the information above, what is the length of the project?

11 days

12 days

14 days

15 days

3 of 3

Question 7. Question :

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors

A -

B -

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the earliest finish time for activity F?

10 days

12 days

14 days

16 days

3 of 3

Question 8. Question :

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors

A -

B -

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the critical path?

ACDFH

IN ACEFH

BCDFH

BCEGH

0 of 3

Question 9. Question :

Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B -

C -

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the slack for activities F and G respectively?

0 days; 0 days

3 days; 0 days

4 days; 3 days

4 days; 0 days

3 of 3

Question 10. Question :

Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:

Immediate

Activity Predecessors

A -

B -

C -

D A, B

E C

F D, E

G E

H F, G

I F

J I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 4

C 5

D 3

E 2

F 1

G 4

H 3

I 2

J 5

Considering the information above, what is the earliest finish time for activity E?

5 days

6 days

7 days

8 days

3 of 3

* Times are displayed in (GMT-05:00) Eastern Time (US & Canada)

Dot Image
Tutorials for this Question
  1. Tutorial # 00036563 Posted By: jack_daneils Posted on: 12/17/2014 11:56 PM
    Puchased By: 10
    Tutorial Preview
    The solution of SAINT GBA334 module 5 quiz 3...
    Attachments
    SAINT_GBA334_module_5_quiz_3.docx (75.74 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    D...an Rating Easily understandable content 07/07/2015
    fa...unga Rating Service cost is pocket-friendly 05/05/2015
    co...odie Rating Professionally written assignments with no-plagiarism 03/08/2015
    ja...ook Rating Satisfied with the solutions 03/04/2015

Great! We have found the solution of this question!

Whatsapp Lisa