PMAN634 Session 9 - Individual Assignment
Question # 00094229
Posted By:
Updated on: 08/18/2015 03:52 PM Due on: 09/17/2015

Given the network plan that follows, compute the early, late, and slack times answer the following:
1. What is the project duration?
2. Using any approach you wish (e.g., trial and error) develop a loading chart for resource resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.
3. Given your resource schedule, compute the early, late, and slack times for your project.
4. Which activities are now critical?
5. What is the project duration now?
Use the templates provided below to construct your charts/tables.
________________________________________
ANSWER:
2 4
C E
0 1 3 3 6
C C
3 3 5 2
C 2-E
1 4
ANSWER:
Carpenter
Electrician
0 1 2 3 4 5 6 7 8 9 10 11 12 13
ANSWER:
ID/RES ES LS EF LF SL
1-C
2-C
3-C
4-E
5-2-E
6-C
1. What is the project duration?
2. Using any approach you wish (e.g., trial and error) develop a loading chart for resource resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.
3. Given your resource schedule, compute the early, late, and slack times for your project.
4. Which activities are now critical?
5. What is the project duration now?
Use the templates provided below to construct your charts/tables.
________________________________________
ANSWER:
2 4
C E
0 1 3 3 6
C C
3 3 5 2
C 2-E
1 4
ANSWER:
Carpenter
Electrician
0 1 2 3 4 5 6 7 8 9 10 11 12 13
ANSWER:
ID/RES ES LS EF LF SL
1-C
2-C
3-C
4-E
5-2-E
6-C

-
Rating:
5/
Solution: PMAN634 Session 9 - Individual Assignment