OPS MGMT Exam 3 Questions
Current Location
Take Test: Exam 3
Assistive Technology Tips [opens in new window]
Instructions
Question Completion Status:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Question 1
A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the first-come-first-served priority rule, what is the number of late (tardy) jobs?
Answer
0 (zero)
1
2
3
4
5 points
Question 2
A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest (earliest) due date rule, what is the average completion (flow) time of all jobs?
Answer
4.0
12.6
2.6
5 points
Question 3
A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating) time priority rule, what will be the average tardiness of these orders?
Answer
2.6
2.0
3.0
5 points
Question 4
A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating) time priority rule, what will be the average number of jobs in the system?
Answer
5
4
3
2.5
5 points
Question 5
A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three hours on machine M2. Job B will take three hours on M1 and two hours on M2. Job C, takes seven hours on M1and three hours on M2. Job D, requires five hours on M1 and one hour on M2. Using Johnson's rule, in what order should these jobs be done? Select one of the following answers.
Answer
ABCD
ACBD
DABC
DACB
5 points
Question 6
Consider the following data for a five-job, 2-machine, flow-shop problem. Find the value of make-span (minimum time to complete all jobs) using the sequence ABCDE. (Note: It is suggested that you draw the Gantt chart first.)
Time Time
Job M1 M2
A 1 2
B 4 2
C 1 3
D 5 4
E 3 5
Answer
16
19
20
30
5 points
Question 7
Which of the following is a measure of whether the job is done ahead of, on, or behind schedule?
Answer
average number of jobs in system
mean flow time
makespan
job tardiness
job lateness
5 points
Question 8
Suppose SPT rule is being used in a "dynamic" scheduling problem. There are five jobs A,B,C,D, and E ready to be processed at the present time. The processing times for the five jobs are 1, 9, 7, 2, and 6 days respectively. A new job F will arrive on the 8th day. The processing time for job F is 5 days. On which day (from present time) job F will be completed?
Answer
25
14
13
5
5 points
Question 9
Johnson's rule gives the optimal answer for which of the following type of problems?
Answer
Minimize make span in a two machine flow shop
Minimize make span in a two machine job shop
Minimize make span in a single machine problem
Minimize make span in both two machine flow and job shops.
5 points
Question 10
Which scheduling rule will minimize the average number of jobs in a single machine scheduling problem?
Answer
First Come First Served (FCFS)
Earliest Due Date (EDD)
Shortest Processing Time (SPT)
Does not matter which rule you use. All rules will give the same answer.
5 points
Question 11
Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration (earliest completion time of the project).
Activity A B C D E F G
Time (days) 5 6 9 4 9 3 4
Answer
21
22
25
28
31
5 points
Question 12
Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. What is the latest start time of activity C if the project completion time (due date) is set at 33 day?
Activity A B C D E F G
Time (days) 5 6 9 4 9 3 4
Answer
5
7
33
Zero (0)
5 points
Question 13
The data for a Time-Cost CPM Scheduling model analysis are given below. The times are in days. What is the minimum cost to complete this project in 14 days? (Hint: This problem requires crashing).
Activity Immediate Predecessor Normal Time Crash Time Normal Cost ($) Crash Cost ($)
A None 4 2 2000 4000
B A 4 3 3000 6000
C A 2 1 2000 2500
D B and C 4 2 5000 5600
E D 3 1 6000 9000
Answer
18,000
27,100
18,300
300
5 points
Question 14
You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the following alternatives gives the probability that the project will be completed by the desired completion date?
Answer
Close to 1.0
Close to 0.3413
Close to 0.8413
Close to 0.5987
Close to 0.0987
5 points
Question 15
Suppose the length of critical path in a project is 50 days. The probability of completing the project within 50 days is:
Answer
Less than 50%
Greater than 50%
Equal to 50%
Can not be determined from the above data
5 points
Question 16
Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing the project is 95%? Round the answer to the nearest higher integer.
Answer
40
41
44
45
5 points
Question 17
The longest path in a network is called the critical path. Is it possible to have more than one critical path in a network?
Answer
yes
no
5 points
Question 18
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis and are given below:
Activity Immediate Predecessor Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($)
A None 3 2 300 400
B A 3 3 100 100
C A 1 1 200 200
D B and C 3 2 400 550
E D 2 1 500 900
F E 3 3 200 200
G F 2 2 100 100
Total indirect costs for 16 days of project duration: $ 600
Total indirect costs for 15 days of project duration: $ 400
Total indirect costs for 14 days of project duration: $ 200
Total indirect costs for 13 days of project duration: $ 100
At what project duration do we achieve the lowest total project cost (i.e., direct plus indirect costs)?
Answer
16 days
15 days
14 days
13 days
5 points
Question 19
Consider a project having the following ten activities. What is the critical path?
Activity A B C D E F G H I J
Immediate Predecessor None None A A, B C, D D C E, G E, F H, I
Time (weeks) 7 3 5 6 4 4 9 8 6 5
Answer
A-C-G-H-J
A-B-C-D-E-F-G-H-I-J
A-D-E-H-J
B-D-F-I-J
5 points
Question 20
Consider a project having the following ten activities. What is the slack time of activity B?
Activity A B C D E F G H I J
Immediate Predecessor None None A A, B C, D D C E, G E, F H, I
Time (weeks) 7 3 5 6 4 4 9 8 6 5
Answer
zero
8
11
3
19
5 points
Save and Submit
Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.
Links to Test Questions and Answers Read question 1 Read answers for question 1 Read question 2 Read answers for question 2 Read question 3 Read answers for question 3 Read question 4 Read answers for question 4 Read question 5 Read answers for question 5 Read question 6 Read answers for question 6 Read question 7 Read answers for question 7 Read question 8 Read answers for question 8 Read question 9 Read answers for question 9 Read question 10 Read answers for question 10 Read question 11 Read answers for question 11 Read question 12 Read answers for question 12 Read question 13 Read answers for question 13 Read question 14 Read answers for question 14 Read question 15 Read answers for question 15 Read question 16 Read answers for question 16 Read question 17 Read answers for question 17 Read question 18 Read answers for question 18 Read question 19 Read answers for question 19 Read question 20 Read answers for question 20
-
Rating:
/5
Solution: OPS MGMT Exam 3 Questions Solution