Module 5 assignment

Question # 00022107 Posted By: neil2103 Updated on: 08/05/2014 07:24 AM Due on: 08/31/2014
Subject Mathematics Topic General Mathematics Tutorials:
Question
Dot Image

Module 5

6.

Given the following network with activity times in months, determine the earliest and latest activity times and slack for each activity.Indicate the critical path and the project duration.

(see diagram in the attached file)

13. Consider the network in problem 6, but with the following new time estimates for each activity:


time estimates (mo)

Activity a m b
1 4 8 12
2 6 10 15
3 2 10 14
4 1 4 13
5 3 6 9
6 3 6 18
7 2 8 12
8 9 15 22
9 5 12 21
10 7 20 25
11 5 6 12
12 3 8 20

Determine the following:
a. Expected activity times
b. Earliest activity times
c. Latest activity times
d. Activity slack
e. Critical path
f. Expected project duration and variance

17. For the CPM/PERT network in Problem 13, determine the probability that the network duration will exceed 50 months.

4. Good project managers are highly sought in business and industry. Describe your experience, if you have worked as a project manager. Alternatively, you can interview someone who may have led a large project in the past.

Dot Image
Tutorials for this Question
  1. Tutorial # 00021444 Posted By: neil2103 Posted on: 08/05/2014 07:26 AM
    Puchased By: 5
    Tutorial Preview
    The solution of Module 5 assignment...
    Attachments
    Module_5_assignment.xlsx (12.08 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    li...ma Rating Live-chat support by the tutors 03/14/2016