What is the first thing the project manager must do before developing a budget in MS Project?

a.Update the project start date

b.Assign costs to various resources in the project

c.Plan the contracting activities

d.Delete any overallocated resources

Where are resource Standard Rates assigned?

a.The Resource Sheet

b.The Gantt Chart

c.The Reports Tab

d.The Project Information Dialog box

What does the Task Usage view show you in addition to the Gantt Chart view?

a.Duration graphs

b.The critical path

c.Resource Titles

d.Task relationship diagram arrows

How is the assignment cost calculated?

a.The work hours divided by the task duration

b.The resource overtime rate added to the standard rate

c.The resource standard rate multiplied by the work hours

d.The work hours multiplied by the task duration

How is the task cost calculated?

a.Summing all the assignment costs for a task

b.Multiplying all the assignment costs for a task

c.Summing the dividend of the remaining assignment costs

d.Summing the product of the remaining assignment costs

 

Dot Image
Tutorials for this Question
  1. Tutorial # 00807736 Posted By: Ferreor Posted on: 10/18/2021 05:52 AM
    Puchased By: 2
    Tutorial Preview
    The solution of MGMT404 2021 September Week 6 Quiz Latest...
    Attachments
    Week_6_Quiz.docx (34.51 KB)

Great! We have found the solution of this question!

Whatsapp Lisa