MGMT404 2021 September Week 6 Quiz Latest

MGMT404 Project Management
Week 6 Quiz
What is the first thing the project manager must do before developing a budget in MS Project?
a.Update the project start date
b.Assign costs to various resources in the project
c.Plan the contracting activities
d.Delete any overallocated resources
Where are resource Standard Rates assigned?
a.The Resource Sheet
b.The Gantt Chart
c.The Reports Tab
d.The Project Information Dialog box
What does the Task Usage view show you in addition to the Gantt Chart view?
a.Duration graphs
b.The critical path
c.Resource Titles
d.Task relationship diagram arrows
How is the assignment cost calculated?
a.The work hours divided by the task duration
b.The resource overtime rate added to the standard rate
c.The resource standard rate multiplied by the work hours
d.The work hours multiplied by the task duration
How is the task cost calculated?
a.Summing all the assignment costs for a task
b.Multiplying all the assignment costs for a task
c.Summing the dividend of the remaining assignment costs
d.Summing the product of the remaining assignment costs

-