Logistics And Operations Management
Question # 00803496
Posted By:
Updated on: 04/23/2021 10:47 AM Due on: 05/19/2021

Q1. A toy company produces talking teddy bears. For the final assembly the head goes through the following three stations: add eyes (10 secs), add nose (10 secs), and add both ears (together 10 secs). In parallel to the head finishing, the torso goes through the three stations: add legs (together 5 secs), add voice module (15 secs), and add arms (together 5 secs). Then the finished head will be attached to the finished body (5 secs). Before the final packing station (10 secs), the teddy receives a bow tie (5 secs). Assume this is a fully automated process.

-