Item Milestone or Deliverable Due Date Actual Date
The PT at Home New Equipment team kicked off their project on 5/1/13. They started creating a project plan on 5/2/13 and completed it one week later on 5/9/13. George approved the plan on 5/14/13, though he was scheduled to approve it on 5/12/13. The team designed the new equipment for two weeks, finishing the design on 5/30/13, two days ahead of schedule. They tested the equipment until 6/6/13 and then took three weeks to build the equipment, finishing on 6/28/13. Their due date was 6/27/13. They retested the equipment for two days, and then completed the project on 7/7/13, one day ahead of schedule.

-