Grand Canyon FIn450 module 2 assignment problems-p 12-3 12-4 12-8 12-12 12-14 and 12-18
|
P 12-3 Breakeven cash inflows and risk Blair Gasses and Chemicals is a supplier of highly |
||||||
|
purified gases to semiconductor manufacturers. A large chip producer has asked Blair |
||||||
|
to build a new gas production facility close to an existing semiconductor plant. Once |
||||||
|
the new gas plant is in place, Blair will be the exclusive supplier for that semiconductor |
||||||
|
fabrication plant for the subsequent 5 years. Blair is considering one of two plant |
||||||
|
designs. The first is Blair’s “standard” plant, which will cost $30 million to build. The |
||||||
|
second is for a “custom” plant, which will cost $40 million to build. The custom plant |
||||||
|
will allow Blair to produce the highly specialized gases that are required for an emerging |
||||||
|
semiconductor manufacturing process. Blair estimates that its client will order |
||||||
|
$10 million of product per year if the traditional plant is constructed, but if the customized |
||||||
|
design is put in place, Blair expects to sell $15 million worth of product annually |
||||||
|
to its client. Blair has enough money to build either type of plant, and, in the absence |
||||||
|
of risk differences, accepts the project with the highest NPV. The cost of capital is 12%. |
||||||
|
a. Find the NPV for each project. Are the projects acceptable? b. Find the breakeven cash inflow for each project. |
||||||
|
c. The firm has estimated the probabilities of achieving various ranges of cash inflows |
||||||
|
for the two projects as shown in the following table. What is the probability |
||||||
|
that each project will achieve at least the breakeven cash inflow found in part b? |
|
d. Which project is more risky? Which project has the potentially higher NPV? |
||
|
Discuss the risk–return trade-offs of the two projects. |
|
e. If the firm wished to minimize losses (that is, NPV 6 $0), which project would |
||||
|
you recommend? Which would you recommend if the goal were to achieve a |
||||
|
higher NPV? |
P 12-4
Basic scenario analysis Murdock Paints is in the process of evaluating two mutually Project A Project B
exclusive additions to its processing capacity. The firm’s financial analysts have developed Initial investment (CF0) ($8,000) ($8,000)
pessimistic, most likely, and optimistic estimates of the annual cash inflows Outcome Annual cash inflows (CF)
associated with each project. These estimates are shown in the following table. Pessimistic $ 200 $ 900
Most likely 1,000 1,000
a. Determine the range of annual cash inflows for each of the two projects. Optimistic 1,800 1,100
|
b. Assume that the firm’s cost of capital is 10% and that both projects have 20-year |
|
lives. Construct a table similar to this one for the NPVs for each project. Include |
|
the range of NPVs for each project. |
c. Do parts a and b provide consistent views of the two projects? Explain.
d. Which project do you recommend? Why?
P 12-8
|
Risk-adjusted discount rates: Basic Country Wallpapers is considering investing in |
|||||||
|
one of three mutually exclusive projects, E, F, and G. The firm’s cost of capital, r, is |
|||||||
|
15%, and the risk-free rate, RF, is 10%. The firm has gathered the basic cash flow |
|||||||
|
and risk index data for each project as shown in the following table. |
|||||||
|
a. Find the net present value (NPV) of each project using the firm’s cost of capital. |
|||||||
|
Which project is preferred in this situation? |
|
b. The firm uses the following equation to determine the risk-adjusted discount |
|
c. Use the RADR for each project to determine its risk-adjusted NPV. Which project |
||||||
|
is preferable in this situation? |
||||||
|
d. Compare and discuss your findings in parts a and c. Which project do you recommend |
|||||||
|
that the firm accept? |
|||||||
P 12-12
|
Risk classes and RADR Moses Manufacturing is attempting to select the best of |
||||||
|
three mutually exclusive projects, X, Y, and Z. Although all the projects have 5-year |
||||||
|
lives, they possess differing degrees of risk. Project X is in class V, the highest-risk |
||||||
|
class; project Y is in class II, the below-average-risk class; and project Z is in class |
||||||
|
III, the average-risk class. The basic cash flow data for each project and the risk |
||||||
|
classes and risk-adjusted discount rates (RADRs) used by the firm are shown in the |
||||||
|
following tables. |
a. Find the risk-adjusted NPV for each project.
|
b. Which project, if any, would you recommend that the firm undertake? |
P12-14
|
Unequal lives: ANPV approach Portland Products is considering the purchase of |
||||||||
|
one of three mutually exclusive projects for increasing production efficiency. The |
||||||||
|
firm plans to use a 14% cost of capital to evaluate these equal-risk projects. The initial |
||||||||
|
investment and annual cash inflows over the life of each project are shown in the |
||||||||
|
following table. |
||||||||
|
a. Calculate the NPV for each project over its life. Rank the projects in descending |
||||||||
|
order on the basis of NPV. |
||||||||
|
b. Use the annualized net present value (ANPV) approach to evaluate and rank the |
||||
|
projects in descending order on the basis of ANPV. |
||||
|
c. Compare and contrast your findings in parts a and b. Which project would you |
||||
|
recommend that the firm purchase? Why? |
P 12-18
|
Capital rationing: IRR and NPV approaches Valley Corporation is attempting to select |
||||||
|
the best of a group of independent projects competing for the firm’s fixed capital |
||||||
|
budget of $4.5 million. The firm recognizes that any unused portion of this budget |
||||||
|
will earn less than its 15% cost of capital, thereby resulting in a present value of inflows |
||||||
|
that is less than the initial investment. The firm has summarized, in the following |
||||||
|
table, the key data to be used in selecting the best group of projects. |
||||||
|
b. Use the net present value (NPV) approach to select the best group of projects. |
||||||
|
c. Compare, contrast, and discuss your findings in parts a and b. |
|
d. Which projects should the firm implement? Why? |
-
Rating:
/5
Solution: Grand Canyon FIn450 module 2 assignment problems-p 12-3 12-4 12-8 12-12 12-14 and 12-18