For this part of this project, you will need to use the POM software:

1. Program the project management problem below and solve it with the use of POM. Select Project Management(PERT/CPM) module, and then select the option File->New->Mean, Stddev given items.

Activity

Mean duration

Std. dev. (days)

A

11

0.9

B

13

1.1

C

7

0.2

D

9

0.8

E

6

1

F

7

1.2

G

10

0.7

H

9

0.6

I

8

0.8

Table 1:Activity, duration and standard deviation

To answer this question:

Answer each question and explain your reasoning or show your calculations.

1. Calculate the project completion time.

2. Indicate the critical path activities.

3. What is the probability of completing this project between 38 and 40 days?

4. What are the slack values for activities C and F? Interpret the meaning of their slack values.

Dot Image
Tutorials for this Question
  1. Tutorial # 00102004 Posted By: kimwood Posted on: 09/24/2015 07:59 PM
    Puchased By: 3
    Tutorial Preview
    or show your calculations. 1. Calculate ...
    Attachments
    Answer_22092015_(3)_Critical_Path_etc._.xlsx (11.05 KB)
    Question_22092015_(3)_Critical_Path_etc._.xlsx.docx (35.18 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    iban...l.com Rating The homework was precisely done 01/02/2016

Great! We have found the solution of this question!

Whatsapp Lisa