Expected Benefits, Which Will Result From Implementation Of The Project And Define Success, Establish:

Question # 00803700 Posted By: Ainsley Updated on: 04/24/2021 10:49 AM Due on: 05/26/2021
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

Question 1

Expected benefits, which will result from implementation of the project and define success, establish:

Question options:

 

how quickly the project must be completed.

 

how much money the customer is willing to pay.

 

the reason the contractor proposes the solution.

 

why the project is being done.

Question 2

The contractor or project team needs to gain agreement from _____ on the project scope document.

Question options:

 

the sponsor or customer

 

only the contractor's chief financial officer

 

only the subcontractors

 

all the stakeholders

Question 3

The project scope document is valuable for establishing:

Question options:

 

a request for proposal for the project.

 

the risk management plan for the project.

 

the contact between the contractor and the customer.

 

a common understanding among project stakeholders regarding the scope of the project.

Question 4

In order to prevent poor quality and avoid quality problems, there needs to be a/an:

Question options:

 

Dot Image

Click chat on right side to get answer. Click on Chat
Whatsapp Lisa