Question 1.
|
Question :
|
(TCO B) Good project cost estimations are
critical to a successful project. With that in mind, compare and contrast
parametric and reserve analysis as cost estimation techniques. Please
provide an example of each.
|
|
Question 2.
|
Question :
|
(TCO A) A company intends to establish a
manufacturing facility by buying an existing factory from a company in the
same industry. A state-of-the art manufacturing line with supporting
utilities will be established in the refurbished factory.
Securing the building will involve negotiating the purchase and
refurbishing and upgrading the building structure.
Utilities that have to be upgraded and new systems installed include an
upgrade of the electrical system, installation of a new compressed air
system, and an increase in the capacity of the plant wastewater treatment
system.
Establishing the manufacturing line will require development of
production equipment specifications, procurement, and installation of
machines and materials handling systems. A systems test plan will be
developed concurrently with preparation of the equipment specifications.
To check out the manufacturing line, a systems test of the complete line
will be performed by operating it to produce product. A separate project
team is handling procurement and stocking of components and materials
that will be needed for the systems test of the new line, as well as when
it becomes fully operational.
Prepare a WBS listing for this project with activities corresponding to a
two-level task and subtask hierarchy. Format the WBS listing with
activity item indents and WBS codes (such as a numbering scheme) that
will clearly identify the level of each activity. Provide columns showing
the WBS code and activities.
|
|
|
|
Question 3.
|
Question :
|
(TCO E) You are assisting on a project for
your organization. An RACI has been created for your project. Your
project manager has asked you to interpret the below RACI.
Project Name: HR software
design
|
RACI
|
Activity
|
PM
|
IT
|
HR
|
Testers
|
Sponsor
|
End User
|
1.1.1 Code software
|
|
R, A
|
|
|
|
C
|
2.1.1 A test code
|
|
|
|
R, A
|
|
|
3.1.1 Incorporate changes
|
A
|
R
|
|
|
|
|
4.1.1 Roll out software
|
A
|
R
|
R
|
|
I
|
C
|
|
|
Question 4.
|
Question :
|
(TCO B) You are the project manager for three
projects. You are about to estimate costs for these three projects. Given
the below information on each project, recommend an appropriate
estimation method and justify your answer for each.
Project A: This project is new to your company. You do not feel confident
in estimating the project costs using internal resources. There are other
companies that have done this type of work. Yet you still want the most
accurate estimates possible.
Project B: The work of this project has not likely been done before by
anyone. You are breaking technological barriers in this project. As such,
it is imperative you get accurate cost estimates.
Project C: This project will be a scale-up of a project done last year.
All the same processes will be used. The costs for the material and other
resources should be scalable based on last year’s costs.
|
|
|
|
Question 5.
|
Question :
|
(TCO C) The SuperFlyer Corporation is developing
a revolutionary flying disc. The new toy can fly straight over a great
distance, which is exciting by itself. However, this disc will also
return to the owner in response to his or her voice! Because this is an
advance over anything that this company has done before, estimating the
amount and cost of the hi-tech materials is difficult. The project
manager recommends using a range estimating process to develop an
estimate. The values below are submitted by the project team.
Current estimates for cost of material are as follows.
Optimistic cost of smart resin:
|
$5.00
|
per lb
|
Most likely cost of smart resin:
|
$6.00
|
per lb
|
Pessimistic cost of smart resin:
|
$7.50
|
per lb
|
Current estimates for total material requirements are as follows.
Optimistic quantity
|
20 lb / 100 units
|
Most likely quantity
|
25 lb / 100 units
|
Pessimistic quantity
|
35 lb / 100 units
|
(a) What is the expected price of the material per pound?
(b) What is the expected amount of material needed for 100 units?
(c) What is the expected cost for 100 units?
|
|
|
Solution: Devry Proj592 quiz 3