DEVRY PROJ420 week 6 QUIZ

(TCO 4) The completion of the Assessment step requires a document produced called the
risk management plan.
risk register.
RBS.
scope.
None of the above
Question 2. Question :
(TCO 4) The risk register includes
risk owners.
identified risks.
risk responses.
implementation actions.
All of the above
Question 3. Question :
(TCO 4) If a risk impacts more than one objective, its risk score is set using
the objective with the highest impact.
the objective that has the highest probability.
the risk with the most impact.
All of the above
None of the above
Question 4. Question :
(TCO 5) The key word in response planning is
identification.
likelihood.
impact.
appropriateness.
Question 5. Question :
(TCO 5) The main output from the response planning step is
updated WBS.
updated risk register.
updated scope.
updated project plan.
Question 6. Question :
(TCO 5) A red risk zone
requires an urgent response.
alerts the PM that they are falling behind schedule.
requires active monitoring of the risk.
is for risks with low impact.
Question 7. Question :
(TCO 6) Transferring a risk is
moving it out of the project.
moving it to a new risk category.
moving it to another project.
moving it to an outside vendor.
:
Question 8. Question :
(TCO 6.) The tools of quantitative risk analysis include
interviewing.
probability distributions.
expert judgments.
All of the above
Question 9. Question :
(TCO 6) The risk register includes
identified risks.
risk responses.
assumptions analysis.
A and B above

-
Rating:
5/
Solution: DEVRY PROJ420 week 6 QUIZ