DEVRY BSOP429 WEEK 5 lab 4

Question # 00022411 Posted By: spqr Updated on: 08/08/2014 01:23 AM Due on: 09/21/2014
Subject Business Topic General Business Tutorials:
Question
Dot Image
Lab 4 of 6: JIT and PAC
Note!

Submit your assignment to the Dropbox located on the silver tab at the top of this page.

(See the Syllabus section "Due Dates for Assignments & Exams" for due dates.)

LAB OVERVIEW

This Lab provides data to use for solving the number of kanbans required for four components at the ABC Company. Use MS Word to copy your answers.

JIT and PAC LabPointsDescription
Component W 5 Calculate the number of kanbans required for Component W using 4 components provided to you.
Component X 5 Calculate the number of kanbans required for Component X using 4 components provided to you.
Component Y 5 Calculate the number of kanbans required for Component Y using 4 components provided to you.
Component Z 5 Calculate the number of kanbans required for Component X using 4 components provided to you.
Total 20 A quality paper will meet the above requirements.

Scenario and Summary

Situation: Solve the number of kanbans required for four components at the ABC Company using the table below.

Component WComponent XComponent YComponent Z

Daily Usage (units)

900 units

250 units

1,200 units

350 units

Lead Time (hours)

2 hours

5 hours

1 hour

3 hours

Container Size (units)

25 units

40 units

50 units

20 units

Safety Stock (percent)

25%

20%

15%

10%


Deliverables

Use the data provided in the table above to calculate the number of kanbans for each component. Please remember to show your work.

LAB STEPS

STEP 1: Component W

Back to Top

Calculate the number of kanbans required for Component W. Copy your completed chart to an MS Word document.

STEP 2: Component X

Back to Top

Calculate the number of kanbans required for Component X. Copy your completed chart to an MS Word document.

STEP 3: Component Y

Back to Top

Calculate the number of kanbans required for Component Y. Copy your work to a MS Word document.

STEP 4: Component Z

Back to Top

Calculate the number of kanbans required for Component Z. Copy your work to an MS Word document.

STEP 5: Submission of Your Assignment

Back to Top

Submit your completed Lab in an MS Word document for grading. Please provide only one document with all responses.

Submit your assignment to the Dropbox located on the silver tab at the top of this page

Dot Image
Tutorials for this Question
  1. Tutorial # 00022459 Posted By: spqr Posted on: 08/15/2014 01:11 PM
    Puchased By: 3
    Tutorial Preview
    The solution of DEVRY BSOP429 WEEK 5 lab 4...
    Attachments
    DEVRY_BSOP429_WEEK_5_lab_4.doc (52 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    kdepa...ail.com Rating Plagiarism and error free content 07/07/2015

Great! We have found the solution of this question!

Whatsapp Lisa