SCM310 Material and Inventory Management

Unit 2 Project  

Part 1: Use the provided MRP template to develop a 6-week manufacturing resource plan (MRP), given the following information:

Download the MRP Template

The finished product being produced requires 1 of component A, 2 of component B, and 0.5 of component C.

The production plan is to have in inventory, ready for sale, 100 units by the end of each of weeks 1–3 and 200 of the finished units by the end of weeks 4–6.

All the components A, B, and C must be available at the beginning of the planned production week.

Lead times from the vendors for A, B, and C are 1, 2, and 3 weeks respectively

Production takes 1 week.

(For example, you would want necessary quantities of A,B, and C in the factory on Monday morning so that the finished units would be available for sale at the end of that same week.)

Part 2: At the bottom of this template, describe the importance of accurate lead time and bill of material information to have an accurate MRP.

Dot Image
Tutorials for this Question
  1. Tutorial # 00797829 Posted By: rey_writer Posted on: 04/09/2021 10:51 AM
    Puchased By: 2
    Tutorial Preview
    The solution of Colorado SCM310 2021 April Unit 2 Project Latest...
    Attachments
    Solution-00797829.zip (113 KB)

Great! We have found the solution of this question!

Whatsapp Lisa