charter oak acc102 week 11 test part 1
·
|
Controlling the materials price variance is usually the responsibility of:
Answer |
· Question 2
3.75 out of 3.75 points
|
2. Controlling the materials quantity variance is usually the responsibility of:
Answer |
||||
· Question 3
3.75 out of 3.75 points
|
3. The use of inexpensive, low quality, materials often results in:
Answer |
||||
· Question 4
3.75 out of 3.75 points
|
4. Excessive overtime hours worked by direct labor workers often results in:
Answer |
||||
· Question 5
3.75 out of 3.75 points
|
5. An unfavorable overhead volume variance results from:
Answer |
||||
· Question 6
0 out of 3.75 points
|
6. If fewer units are produced than had been estimated when standard unit costs were determined, there would normally be: Answer |
||||
· Question 7
3.75 out of 3.75 points
|
7. Overhead volume variances indicate: Answer |
||||
· Question 8
3.75 out of 3.75 points
|
8. Which statement is true regarding a standard cost system? Answer |
||||
· Question 9
3.75 out of 3.75 points
|
9. The overhead spending variance: Answer |
||||
· Question 10
3.75 out of 3.75 points
|
Use the following to answer questions 10-12: Tony's Inc. flexible budget for June, based upon actual output, called for the use of 10,000 pounds of materials at a standard cost of $6.10 per pound. The Production Department actually used 10,300 pounds of materials costing $5.80 per pound during June. 10. Refer to the information above. Tony's materials price variance for June is:
Answer |
||||
· Question 11
3.75 out of 3.75 points
|
11. Refer to the information above. The materials quantity variance for Tony's June operations is: Answer |
||||
· Question 12
3.75 out of 3.75 points
|
12. Refer to the information above. The journal entry to record the cost of direct materials used in June includes each of the following except: Answer |
||||
· Question 13
3.75 out of 3.75 points
|
Use the following to answer questions 13-16: Seaside Company's flexible budget, based upon the number of equivalent units produced, called for the use of 5,000 square yards of fabric at a standard cost of $2.10 per square yard. The Production Department actually used 5,200 square yards costing $1.95 per square yard during June. 13. Refer to the information above. The materials price variance for Seaside Company for June is:
Answer |
||||
· Question 14
3.75 out of 3.75 points
|
14. Refer to the information above. The materials quantity variance for Seaside Company for June is: Answer |
||||
· Question 15
3.75 out of 3.75 points
|
15. Refer to the information above. The journal entry to record the cost of direct materials used in March includes: Answer |
||||
· Question 16
3.75 out of 3.75 points
|
16. Refer to the information above. With respect to materials costs, the supervisor of the Production Department should be held responsible for: Answer |
||||
· Question 17
3.75 out of 3.75 points
|
Use the following to answer questions 17-20: Vista Mfg.'s July production involved actual direct labor costs of $46,287 for 3,700 direct labor hours. The budget for the July level of production called for 3,800 direct labor hours at $12.50 per hour, using a standard cost system. 17. Refer to the information above. With respect to labor costs, Vista/>'s production manager is responsible for:
Answer |
||||
· Question 18
3.75 out of 3.75 points
|
18. Refer to the information above. Vista/>'s labor rate variance for July is: Answer |
||||
· Question 19
3.75 out of 3.75 points
|
19. Refer to the information above. Vista/>'s labor efficiency variance for July is: Answer |
||||
· Question 20
3.75 out of 3.75 points
|
20. Refer to the information above. Which of the following is the most likely explanation for the types of labor variances resulting from Vista/>'s July operations? Answer |
||||
\
-
Rating:
/5
Solution: charter oak acc102 week 11 test part 1