Chapter 7 Constraint Management

Question # 00051256 Posted By: solutionshere Updated on: 02/28/2015 07:29 AM Due on: 02/28/2015
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

44) Use the information in Table 7.2. What is the capacity for the A-B-C-E process route?

A) 10 students per hour

B) 6 student per hour

C) 3.5 students per hour

D) 2.9 students per hour

45) Use the information in Table 7.2. What is the capacity for the A-B-D-E process route?

A) 10 students per hour

B) 6 student per hour

C) 3.5 students per hour

D) 2.9 students per hour

46) Use the information in Table 7.2. If 60% of the students are routed to C and 40% are routed to D, what is the average capacity per hour for the process?

A) 10 students per hour

B) 6.5 student per hour

C) 8 students per hour

D) 8.4 students per hour

47) Use the information in Table 7.2. Where would you expect student wait times to occur?

A) D only

B) B, C and D

C) A only

D) E only


Table 7.3

The figure above shows the process for customers arriving at Pierre's Spa and Salon. After signing in, customers are routed to different locations in the Spa for the two different services provided. The numbers in parentheses are the time in minutes for each step of the process.

48) Use the information in Table 7.3. What is the throughput time for the A-B-C-D -H routing?

A) 48 minutes

B) 30 minutes

C) 53 minutes

D) 23 minutes

49) Use the information in Table 7.3. What is the throughput time for the A-B-E-F-G-H routing?

A) 48 minutes

B) 30 minutes

C) 53 minutes

D) 23 minutes

50) Use the information in Table 7.3. What is the process bottleneck?

A) H

B) B

C) C

D) D


Table 7.4

The figure above shows the process for customers arriving at Hobbies Unlimited for several advertised crafts demonstrations. After signing in, customers are routed to different locations in the store for the two different programs provided. The numbers in parentheses are the time in minutes for each step of the process.

51) Use the information in Table 7.4. What is the throughput time for the A-B-C-D-G routing?

A) 25 minutes

B) 70 minutes

C) 105 minutes

D) 60 minutes

52) Use the information in Table 7.4. What is the throughput time for the A-B-E-F-G routing?

A) 25 minutes

B) 70 minutes

C) 105 minutes

D) 60 minutes

53) Use the information in Table 7.4. How many customers can be processed through the A-B-C-D-G routing during a 4-hour evening session?

A) 48

B) 24

C) 32

D) 12


Dot Image
Tutorials for this Question
  1. Tutorial # 00048353 Posted By: solutionshere Posted on: 02/28/2015 07:31 AM
    Puchased By: 4
    Tutorial Preview
    students per hour D) 2.9 students per hour Answer: A Reference: ...
    Attachments
    chupter.docx (117.78 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    an...ouse Rating Instant customer chat support 11/30/2016
    Nic...ford Rating Really appreciable tutorial service 06/03/2015

Great! We have found the solution of this question!

Whatsapp Lisa