Chapter 11 Project Management

Question # 00036013 Posted By: solutionshere Updated on: 12/12/2014 06:53 AM Due on: 12/12/2014
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

126) An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity.

Activity

Expected time (weeks)

Budgeted

Cost

Immediate Predecessors

A

3

$2,000

None

B

4

$6,000

None

C

2

$7,000

A

D

5

$9,000

B

E

3

$3,000

C

F

6

$8,000

B,D

Develop a budget for the 15 weeks of the project using ES times.


127) An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity.

Activity

Expected time (weeks)

Budgeted Cost

Immediate Predecessors

A

3

$2,000

None

B

4

$6,000

None

C

2

$7,000

A

D

5

$9,000

B

E

3

$3,000

C

F

6

$8,000

B,D

Develop a budget for the 15 weeks of the project using LS times.

128) Activity C of a project has a budgeted cost of $40,000 and is 20% complete. The actual cost is $10,000.

(a) What is the value of work completed?

(b) What is the activity difference?

129) Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).

Activity

Immediate

Predecessor

a

m

b

A

--

2

5

8

B

A

3

6

9

C

A

4

7

10

D

B

2

5

14

E

D

3

3

3

F

C

6

8

10

G

E, F

1

1

1

H

C

6

10

14

I

G, H

3

4

5

(a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost?

(b) What would be the added cost if you wanted to complete the project in the minimum time possible?

130) PERT is the acronym for what?

131) In a PERT analysis, how is the optimistic time defined?


132) CPM is the acronym for what?

133) In PERT analysis, how is the pessimistic activity time defined?

134) In PERT/CPM, what is meant by the critical path?

Dot Image
Tutorials for this Question
  1. Tutorial # 00035298 Posted By: solutionshere Posted on: 12/12/2014 06:56 AM
    Puchased By: 5
    Tutorial Preview
    for the 15 weeks of the project using LS times. Answer: ...
    Attachments
    Solution-00035298.zip (115 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    ha...101 Rating Diverse range of tutorials on all subjects 12/27/2017
    Ja...tel Rating Instant customer support services 12/27/2017
    ski...1226 Rating Tutorials prepared by experts 08/24/2015

Great! We have found the solution of this question!

Whatsapp Lisa