Chapter 11 Project Management

Question # 00036001 Posted By: solutionshere Updated on: 12/12/2014 06:21 AM Due on: 12/12/2014
Subject General Questions Topic General General Questions Tutorials:
Question
Dot Image

31) In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the critical path.

32) Given the assumptions in PERT, the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.

33) Gantt charts and PERT diagrams provide the same information, just in different formats.

34) Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities.

35) Budgets are computed using only ES times.

36) The value of work completed is computed by multiplying budgeted cost by the percent completion.


37) Shortening a project is called crashing.

38) The activity crash cost is equal to the incremental cost of shortening the project.

39) The critical path of a network is the

A) shortest time path through the network.

B) path with the fewest activities.

C) path with the most activities.

D) longest time path through the network.

E) None of the above

40) In a PERT network, the earliest (activity) start time is the

A) earliest time that an activity can be finished without delaying the entire project.

B) latest time that an activity can be started without delaying the entire project.

C) earliest time that an activity can start without violation of precedence requirements.

D) latest time that an activity can be finished without delaying the entire project.

E) None of the above

41) Slack time in a network is the

A) amount of time that an activity would take assuming very unfavorable conditions.

B) shortest amount of time that could be required to complete the activity.

C) amount of time that you would expect it would take to complete the activity.

D) difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.

E) amount of time that an activity can be delayed without delaying the entire project.

42) The first step in planning and scheduling a project is to develop the

A) employee scheduling plan.

B) PERT/CPM network diagram.

C) critical path.

D) work breakdown structure.

E) variance calculations for each activity.

43) Which of the following is not a concept associated with CPM?

A) normal time

B) probability

C) normal cost

D) crash cost

E) deterministic network

44) PERT

A) assumes that we do not know ahead of time what activities must be completed.

B) assumes that activity time estimates follow the normal probability distribution.

C) is a network technique that uses three time estimates for each activity in a project.

D) is a deterministic network technique that allows for project crashing.

E) None of the above

45) CPM

A) assumes we do not know ahead of time what activities must be completed.

B) assumes that activity time estimates follow the normal probability distribution.

C) is a deterministic network technique that allows for project crashing.

D) is a network technique that allows three time estimates for each activity in a project.

E) None of the above

46) Managers use the network analysis of PERT and CPM to help them

A) derive flexibility by identifying noncritical activities.

B) replan, reschedule, and reallocate resources such as manpower and finances.

C) plan, schedule, monitor, and control large and complex projects.

D) All of the above

E) None of the above


47) The expected time in PERT is

A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.

B) the modal time of a beta distribution.

C) a simple average of the most optimistic, most likely, and most pessimistic times.

D) the square root of the sum of the variances of the activities on the critical path.

E) None of the above

48) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.

A) 8

B) 6

C) 7

D) 9

E) None of the above

49) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.

A) 6

B) 7

C) 9

D) 5

E) None of the above

50) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.

A) 14

B) 12

C) 11

D) 13

E) None of the above


Dot Image
Tutorials for this Question
  1. Tutorial # 00035287 Posted By: solutionshere Posted on: 12/12/2014 06:22 AM
    Puchased By: 3
    Tutorial Preview
    longest time path through the network. E) None of the ...
    Attachments
    Solution-00035287.zip (80 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    H...e11 Rating Plagiarism-free and error-free assignments 09/02/2016

Great! We have found the solution of this question!

Whatsapp Lisa