I need assistance in answering one question in Excel using a feature called Crystal Ball I need the response back today ASAP

 

  1. You have a network with a critical path A-B-C-D.  The values for optimistic (a), pessimistic (b) and most likely (m) durations for each task are as shown below.   

Task

a

m

b

Te

Var

A

6

8

12

 

 

B

3

4

6

 

 

C

3

9

12

 

 

D

5

5

7

 

 

 

    1. What is the value of μ for the network?
    2. What is the value of σμ2 for the network?
    3. What is the probability that this network can be finished within 27 days?

 

 