1 Slack of an activity can be calculated by subtracting the earliest start time of the activity from its earliest finish time.

True

False

2  In the Southwestern University case, what is the project duration?

 215

230

None of these

245

3 Read the "Project management at Southwestern University" case. Which one is the network diagram of the project in the case?

4Earliest finish time of an activity is equal to the sum of its earliest start time and its duration

True

 False

 