Assume that you are the manager of a shop

Question # 00384228 Posted By: rey_writer Updated on: 09/11/2016 07:41 AM Due on: 09/11/2016
Subject Business Topic Management Tutorials:
Question
Dot Image

Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is


Item

Lead Time (weeks)

On Hand

Components

Saw

2

15

A(2), B(1), C(4)

A

1

10

E(3), D(1)

B

2

5

D(2), F(3)

C

2

65

E(2), D(2)

D

1

20

E

1

10

F

2

30


b.

Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)


Item: E(3) & E(2) LT = 1 wk.

Beg. Inv.

1

2

3

4

5

6

7

8

Gross requirements

Scheduled receipts

Projected on hand

Net requirements

Planned order receipt

Planned order release

Dot Image
Tutorials for this Question
  1. Tutorial # 00379163 Posted By: rey_writer Posted on: 09/11/2016 07:42 AM
    Puchased By: 3
    Tutorial Preview
    The solution of Assume that you are the manager of a shop...
    Attachments
    Assumption.docx (12.16 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    g...mar Rating All doubts are cleared easily 06/08/2018

Great! We have found the solution of this question!

Whatsapp Lisa