Assume that you are the manager of a shop
Question # 00384228
Posted By:
Updated on: 09/11/2016 07:41 AM Due on: 09/11/2016

Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is |
Item | Lead Time (weeks) | On Hand | Components |
Saw | 2 | 15 | A(2), B(1), C(4) |
A | 1 | 10 | E(3), D(1) |
B | 2 | 5 | D(2), F(3) |
C | 2 | 65 | E(2), D(2) |
D | 1 | 20 | |
E | 1 | 10 | |
F | 2 | 30 |
b. | Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.) |
Item: E(3) & E(2) LT = 1 wk.
Beg. Inv.
1
2
3
4
5
6
7
8
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned order receipt
Planned order release

-