ACCT 300-Dillon Aerospace Company contracted to

Question # 00571253 Posted By: rey_writer Updated on: 08/04/2017 09:33 AM Due on: 08/04/2017
Subject Accounting Topic Accounting Tutorials:
Question
Dot Image

Dillon Aerospace Company contracted to build a plane for $8,000,000. Construction began in 2016 and was completed in 2017. Data related to construction are:


2016 2017

Costs incurred during the year $2,640,000 $2,200,000

Estimated costs to complete $2,160,000 0


1.Prepare entries to record revenue and gross profit for 2016 and 2017 using the percentage of completion method.

2. Prepare the appropriate entry to record revenue and gross profit in 2017 assuming the completed contract method is used.

Dot Image
Tutorials for this Question
  1. Tutorial # 00568959 Posted By: rey_writer Posted on: 08/04/2017 09:33 AM
    Puchased By: 3
    Tutorial Preview
    The solution of ACCT 300-Dillon Aerospace Company contracted to...
    Attachments
    CH_Lux.xlsx (9.74 KB)
    Recent Feedback
    Rated By Feedback Comments Rated On
    Mk...ifi Rating Tutors expertise in their field of interest 11/30/2017

Great! We have found the solution of this question!

Whatsapp Lisa