A project to remodel a garage has the following activities
ar.tamanna
Question:
Please reply me with solutions and calculations as soon as possible. I have 45 minutes
(TCO C) A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
ActivityDurationPredecessors
A4 months---
B3 months---
C3 months---
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
- What are the critical path activities? (8 points)
- What is the project's scheduled completion time? (8 points)
- What is the slack or float for Activity C? Show your calculations. (8 points)
- What is the slack or float for Activity D? Show your calculations. (8 points)
- What is the slack or float for Activity F? Show your calculations. (8 points)
(Points : 40)
(TCO A) In the _____ organization structure, the project manager is responsible for the project results. He or she controls all the project resources and employs cross-functional teams to accomplish the project. |
Weak Matrix
Strong Matrix
Pure Project
Functional
(TCO A) The project plan is executed in the _____. (Points : 10) |
initiating phase
planning phase
executing phase
closing phase
TCO F) It is important to use the _____ as the standard against which actual cost is compared. (Points : 10) |
cumulative budget
total budget
budget at completion
phased budget
TCO H) A project audit provides an opportunity to evaluate issues and concerns to determine potential improvements. A project audit should contain the following information. (Points : 10) |
Project charter, scope, and assumptions
Risk assessment, future projections, and audit limitations
Resource skills and assignments
Communications management plan
-
Rating:
/5
Solution: A project to remodel a garage has the following activities