ActivityDurationPredecessors
A2 months---
B4 months---
C4 months---
D1 monthA
E5 monthsB
F2 monthsB, C
G1 monthC
H3 monthsE, F, G
I2 monthsD, E
J2 monthsG, H
- What are the critical path activities? (10 points)
- What is the project's scheduled completion time? (10 points)
-