Question One

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

 

1 Marks

What are the main processes involved in project time management? In your words please describe them to help students in high school to perform their final project?

Hint: What’s really challenging here that the language and description of each process should be easy and understandable by students did not study project management subject at all. (show me your innovative ways to transfer your experience and knowledge in stating, defining, and illustrating (graphs may be used).

Question two

2.5 Marks

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

Suppose a project X is half completed by the end of first month. Upto this duration the rate of performance is 50 percent.

Complete the below table by using given values and explain about the budget and schedule on the basis of calculations.

Earned value calculations for project X after 1 month are as follows:

PV=8000 SR AC=20000 SR RP=50%

Project X

Duration (1 Month)

Earned Value (EV)

Planned Value (PV)

Actual cost (AC)

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI)

Schedule Performance Index (SPI)

Question three

1 Marks

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

Describe Testing tasks in the software development life cycle?

Question four

1.5 Marks

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

The following table shows the tasks, dependencies, and estimated times a project manager might input. Please use the details below to draw a GANTT chart for a software development project? (The project Starting date 12/06/2019)

Task Identifier

Task Description

Predecessor Task(s)

Time (days)

 

1

 

Establish project

 

-

 

2

 

2

 

Establish customer requirements

 

1

 

3

 

3

 

Produce software specification documents

 

2

 

4

 

4

 

Write test plans

3

1

5

Write code

3

2

6

Developer testing

5

2

7

System testing

4,6

4

8

Write customer documentation

3

3

 

Dot Image
Tutorials for this Question
  1. Tutorial # 00719331 Posted By: dr.tony Posted on: 03/22/2019 01:15 PM
    Puchased By: 2
    Tutorial Preview
    The solution of IT Project Management...
    Attachments
    IT_Project_Management.ZIP (18.96 KB)

Great! We have found the solution of this question!

Whatsapp Lisa